Uttar Pradesh Real Estate Regulatory Authority

Suresh Chand Sharma v. Rise Projects Pvt Ltd

Complaint No. NCR145/07/111181/2023

Decision date
Not recorded
Text availability
Machine-read (OCR) text, unverified
Bench
Adjudicating Officer Gautam Budh Nagar
Counsel
Puneet Jain (in this matter)

Source: UP RERA order

Connected provisions and cases

No further provision or case links are recorded.

Judgment text

English translation. Machine translation from the Hindi by AI (Claude Haiku), not reviewed. The original order below is the authoritative text.

UP Real Estate Regulatory Authority, Regional Office, Gautam Buddh Nagar Hearing Bench-II 47. Complaint No.: NCRI45/07/8/2023 Suresh Chand Sharma vs. Rise Projects Private Limited Date: 23/11/2023 The complainant's case under Section 34 was presented through video conferencing. When the matter was called, the learned advocates of both parties appeared. The respondent is directed to upload its written reply on the RERA portal within 4 weeks in respect of the [?] complaint, and to state in its written reply the confirmation of the amount received from the complainant. The case file is to be presented for reply / arguments on 24.02.2024. (Member), UP Real Estate Regulatory Authority

Original order

उ0प्र0 भू-सम्पदा विनियामक प्राधिकरण, क्षेत्रीय कार्यालय, गौतमबुद्धनगर सुनवाई पीठ-॥ 47 -शिकायत संख्या — NCRI45/07/8/2023 सुरेश चंद शर्मा बनाम राइज प्रोजेक्ट्स प्राइवेट लिमिटेड दिनांक :- 23 /44 / 2023 शिकायतकर्ता का वाद धारा-34 के अन्तर्गत वीडियो कॉन्फ्रेंसिंग के माध्यम से प्रस्तुत किया war) पुकार पर उभयपक्ष के अधिवक्तागण उपस्थित हुए। विपक्षी को निर्देशित किया जाता है कि वह ved शिकायत के सम्बन्ध में 4 सप्ताह के अन्दर अपना लिखित उत्तर रेरा पोर्टल पर अपलोड करना सुनिश्चित करें, साथ ही शिकायतकर्ता से प्राप्त धनराशि की पुष्टि भी अपने लिखित उत्तर में अंकित करना सुनिश्चित करें। पत्रावली वास्ते उत्तर “बहस हेतु दिनांक 24.02.2024 को पेश हो। टी उ0प्र0 भू-सम्पदा विनियामक प्राधिकरण