Uttar Pradesh Real Estate Regulatory Authority
Nitin Batra v. Project Category-Un-Register Wave Megacity Centre Pvt. Ltd
Complaint No. NCR144/11/65473/2020
- Decision date
- Not recorded
- Text availability
- Machine-read (OCR) text, unverified
- Bench
- Adjudicating Officer Gautam Budh Nagar
Source: UP RERA order
Connected provisions and cases
No further provision or case links are recorded.
Judgment text
प उ0प्र0 भू-सम्पदा विनियामक प्राधिकरण, क्षेत्रीय कार्यालय, गौतमबुद्धनगर। पीठ-2 उपस्थिति :- श्री बलविन्दर कुमार, सदस्य शिकायत संख्या :--0८0२44/] /65473/2020 नितिन बत्रा बनाम aq मेगासिटी सेन्टर प्रा० लि० प्रस्तुत शिकायत प्रार्थना पत्र शिकायतकर्ता द्वारा विपक्षी के विरुद्द कब्जा एवं विलम्बित अवधि का ब्याज दिलाये जाने हेतु संस्थित किया गया है। संक्षेप में शिकायतकर्ता का कथन है कि उनके द्वारा विपक्षी की परियोजना में यूनिट wo-E-50i, AMOR TOWER बुक किया गया, जिसके लिए उनके द्वारा समय-समय पर किश्तों के आधार पर ,37,03,400 / - रुपये का भुगतान किया गया। विपक्षी द्वारा परियोजना पूर्ण कर दिनांक 24.2.2046 तक कब्जा दिया जाना था, परन्तु विपक्षी द्वारा शिकायतकर्ता को अभी तक कब्जा नहीं दिया गया। अतः शिकायतकर्ता द्वारा कब्जा एवं विलम्बित अवधि का ब्याज दिलाये जाने का अनुरोध किया गया है। शिकायतकर्ता की ओर से अपने कथन के समर्थन में आवेदन फार्म, सेंगशन लैटर, खाता विवरण आदि की छायाप्रतियां दाखिल की गयी हैं। प्राधिकरण की ओर से विपक्षी को नोटिस जारी करते हुए सूचित किया गया था कि निर्धारित तिथि पर उपस्थित होकर आवश्यक साक्ष्यों सहित अपना लिखित अभिकथन प्रस्तुत करें। विपक्षी विभिन्न तिथियों पर उपस्थित रहा है, जिसमें उन्हें निर्देशित किया गया था कि वह अग्रिम नियत तिथि पर प्रतिवाद मं) दाखिल करें। विपक्षी को पर्याप्त अवसर दिये जाने पर भी कोई है! पत्र Page दाखिल नहीं किया गया, परन्तु अंतिम सुनवाई दिनांक 07.04.2024 को की गयी जिसमें विपक्षी उपस्थिति थे, परन्तु उनके द्वारा प्रतिवाद पत्र दाखिल नहीं किया “गया है। शिकायतकर्ता को सुना व पत्रावली का अवलोकन किया।
पक्षकारों के अभिवचनों के आधार पर निम्नलिखित वाद बिन्दु विचारणीय किये गये :- 4... क्या रेरा से पूर्व के अनुबन्ध WS दायरे में नहीं आते ? 2. क्या अनुबन्ध में आर्बिट्रेशन क्लॉज होने के कारण वाद की सुनवाई का क्षेत्राधिकार इस पीठ को है ? 3. क्या शिकायतकर्ता कब्जा एवं विलम्बित अवधि का ब्याज पाने का अधिकारी है? निस्तारण बिन्दु संख्या-॥ बिन्दु सं)-। इस आशय का विरचित किया गया है कि क्या रेरा से पूर्व के अनुबन्ध रेरा के दायरे में नहीं आते ? यह बिन्दु विपक्षी के अभिकथनों पर विरचित किया गया है, जिसे साबित करने का भार विपक्षी पर है। इस सम्बंध में माननीय बॉम्बे उच्च न्यायालय द्वारा Re याचिका संख्या- 2737 /20i7 नीलकमल Raced सबअर्बन प्राणललि0 एवं अन्य बनाम यूनियन ऑफ इंडिया में दिया गया आब्जर्वेशन महत्वपूर्ण है। जिसमें स्पष्ट रूप से उल्लिखित किया गया है कि :- "The provisions of RERA, however, do not rewrite the clause of completion or handing over possession in agreement for sale. Section 4(2)0)(0) enables the promoter to give fresh time line independent of the time period stipulated in the agreements for sale entered into between him and the allottees so that he is not visited with penal consequences laid down under RERA. In other words, by giving opportunity to the promoter to prescribe fresh time line under —————————enee Page 2 age 2 Section 4(2)(0)(0) he is not absolved of the liability under the agreement for sale."
॥ उपरोक्त विधि व्यवस्था से यह स्पष्ट है कि रेरा के प्राविधान के अनुसार अनुबन्ध में दिये गये पूर्णता एवं कब्जे देने के प्रस्तर का पुनर्लेखन नहीं किया जा सकता। धारा 4(2)0)(सी) के अन्तर्गत प्रोमोटर एक नई समय सीमा दे सकता है, जो कि अनुबन्ध पर निर्भर नहीं होगा किन्तु उक्त समय सीमा रेरा में दिये गये “पीनल waitin” से बचा सकता है किन्तु उससे वह अनुबन्ध में दिये गये उत्तरदायित्वों से मुक्त नहीं होगा। इससे अवधारित किया जा सकता है कि प्रोमोटर अनुबन्ध में दिये गये कब्जे की तिथि के लिए उत्तरदायित्व है एवं विलम्ब की गणना अनुबन्ध की तिथि के अनुसार की जायेगी वैसे भी ऑनगोईंग परियोजना रेरा की परिधि में आते है। dager बिन्दु संख्या ॥ निस्तारित किया जाता है। निस्तारण बिन्दु wo 2 विपक्षी की ओर से यह भी तर्क प्रस्तुत किया गया है कि अनुबन्ध में आर्बट्रेशन का क्लाज है, जिस कारण शिकायतकर्ता व विपक्षी के मध्य किसी भी विवाद को केवल आर्बीट्रेटर के माध्यम से ही Pena किया जा सकता है और इस पीठ को इस शिकायत को सुने जाने की क्षेत्राधिकारिता प्राप्त नही है। इस सम्बंध में उल्लेखनीय है माननीय उच्चतम न्यायालय द्वारा एमआर एम.जी.एफ. बनाम आफताब सिंह में अभिनिर्धारित किया गया है कि :- (i) the disputes which are to be adjudicated and governed by statutory enactments, established for specific public purpose to sub-serve a particular public policy are not arbitrable; (ii) there are vast domains of the legal universe that are non-arbitrable and kept at a distance from private dispute resolution;
(iii) the subject amendment was meant for a completely different purpose, leaving status quo ante unaltered and subsequently reaffirmed and restated by the Hon'ble Supreme Court; माननीय उच्चतम न्यायालय द्वारा पारित उपरोक्त विधि व्यवस्थाओ के आलोक में यह स्पष्ट है कि कुछ विवादों का निराकरण आरिंट्रेटर द्वारा आर्बिट्रेशन अनुबन्ध के पश्चात् भी नहीं की जा सकती है। विशेष रूप से गठित प्राधिकरणों का क्षेत्राधिकार मात्र आर्बिट्रेशन क्लॉज के आवरण से बेदखल नहीं किया जा सकता है। ऐसे सभी विवाद जिसके लिए विधि द्वारा विशेष निकाय बनाये गये है और इसका क्षेत्राधिकार दिया गया है, इस प्रकार विवाद को Arata करने के लिए आर्बिट्रेटर सक्षम नहीं है। उपरोक्त विधि व्यवस्थाओं के प्रकाश में यह स्पष्ट है कि भू-सम्पदा विनियामक एवं विकास प्राधिकरण - अधिनियम 2046 की धारा 79, आर्बिट्रेशन एक्ट पर अभिभूत होगा। एन.सी.डी. ae. ने ए.अय्यास्वामी में दिए तर्क को लागू करने के लिए यह निष्कर्ष निकाला है कि एक ही सिद्धांत रियल एस्टेट अधिनियम के तहत उक्त मामलों में लागू हो सकता है, जो कि गृहक्रेताओं एवं facet के बीच विवादों के समाधान के लिए एक विशेष तंत्र प्रदान करता है। उपरोक्त प्रतिपादित सिद्धांतों को दृष्टिगत रखते हुए विपक्षी द्वारा आर्बिट्रेटः को संदर्भित करने का प्रश्न स्वतः समाप्त हो जाता है। dager बिन्दु सं० 2 निस्तारित किया जाता है। निस्तारण बिन्दु do 03 शिकायतकर्ता का कहना है कि विपक्षी द्वारा अभी तक कब्जा नहीं दिया गया है, जिस कारण शिकायतकर्ता द्वारा कब्जा एवं विलम्बित अवधि का ब्याज दिलाये जाने का अनुरोध किया गया है। शिकायतकर्ता द्वारा कहा गया है कि विपक्षी द्वारा दिनांक 24.2.2046
तक कब्जा दिया जाना था। विपक्षी द्वारा विलम्बित अवधि का ब्याज अदा नहीं किया जा रहा है। शिकायतकर्ता द्वारा अपने कथन के समर्थन में आवंटी अरेंजमेंट अनुबन्ध की छायाप्रति दाखिल नहीं की गयी है, जिससे स्पष्ट हो सके कि विपक्षी द्वारा कब तक कब्जा दिया जाना था, परन्तु शिकायतकर्ता द्वारा कहा गया है कि विपक्षी द्वारा दिनांक 24.:220i6 तक कब्जा दिया जाना था। ऐसे में उपरोक्तानुसार कब्जे की तिथि 24.42.2046 होती है। यह स्पष्ट है कि परियोजना विलम्बित है और ऐसे में शिकायतकर्ता दिनांक 22.:220i6 से ओ.सी. /सी.सी. प्राप्त होने अथवा कब्जा ऑफर किये जाने, जो भी बाद में हो तक की अवधि पर विलंबित अवधि का ब्याज पाने का . अधिकारी है। इस सम्बंध में उल्लेखनीय है कि माननीय बॉम्बे उच्च न्यायालय के नीलकमल रियलटर्स सबअर्बन प्रालि. आदि बनाम यूनियन ऑफ इंडिया की याचिका में माननीय बॉम्बे उच्च न्यायालय द्वारा अभिनिर्धारित किया गया है कि :-
"Section 8()(b) lays down that if the promoter fails to complete or is unable to give possession of an aprtment due to discontinuance of his business as a developer on account of suspension or revocation of the registration under the Act or for any other reason, he is liable on demand to the allottees, in case the allottee wishes to withdraw from the project, without prejudice in this hehalf including compensation. If the allottee does not intent to withdraw from the project he shall be paid by the promoter interest for every month's delay till handing over of the possession,. The requirement to pay interest is not a penalty as the payment of interest is compensatory in nature in the light of the delay suffered by the allottee who has paid for his apartment but has not received possession of it. The obligation imposed on the promoter to pay interest till such time as the apartment is handed over to him is not unreasonable." अतः उपरोक्त निर्णय के आलोक में यह स्पष्ट है कि रेरा के प्राविधानों के अन्तर्गत प्रमोटर व क्रेता के बीच किये गये अनुबंध के अनुरूप विलम्ब तथा मूल धनराशि पर ब्याज देय होगा, क्योंकि प्रमोटर्स द्वारा ved धनराशि का उपभोग किया गया है।
जहां तक देय ब्याज दर का प्रश्न है, राज्य सरकार द्वारा भू-सम्पदा (विनियमन एवं विकास) अधिनियम 20i6 के अधीन दिनांक 47.40.2048 को भू-सम्पदा (विनियमन और विकास) (विक्रय /पट्टा के लिए करार) नियमावली 20i8 अधिसूचित की गयी हैं। इसमें dome के रूप में दिये गये विक्रय /पट्टा विलेख के प्रारूप के प्रस्तर 9 में प्रमोटर्स के डिफाल्ट प्रकरण ह (Events of default) परिभाषित है, जिसमें प्रस्तर 9.2 (ii) F we के डिफाल्टर होने की स्थिति में आवंटी हेतु प्राविधानित है किः- "The Allottee shall have the option of terminating the Agreement in which case the Promoter shall be liable to refund the entire money paid by the Allottee under any head whatsoever towards the purchase of the apartment, along with interest at the rate equal to MCLR (Marginal Cost of Lending Rate) on home loan of State Bank of India +I% unless provided otherwise under the Rules. within forty-five days of receiving the termination notice:" यही दर आवंटियों के द्वारा डिफॉल्ट की स्थिति में भी प्रस्तर 9.30) में निर्धारित है। उक्त प्राविधान को दृष्टिगत रखते हुए आवंटी को MCIR+I प्रतिशत की ब्याज दर पर विलम्बित अवधि का ब्याज दिलाया जाना न््यायोचित प्रतीत होता है। जहां तक किस अवधि तक का ब्याज दिलाये जाने का प्रश्न है। इस सम्बंध में सिविल अपील Wo 6649-50 ,/ 208 सुपरटेक लिमिटेड बनाम रजनी गोयल में माननीय उच्चतम न्यायालय द्वारा अभिनिर्धारित किया गया है कि :-
"The period of Interest should close on April 20i6 when the Full Occupancy Certificate was obtained as per the admission of the Respondent — Purchaser herself in Para 4(j) of the Consumer Complaint, wherein she has admitted that the Appellant —Builder had obtained the Completion Certificate as late as April 206. The Respondent — Purchaser could not have any further grievance after April 206 with respect to delay in handing over possession. The Respondent - Purchaser ought not to be allowed to reap the benefits of her own delay in taking possession. " उपरोक्त विधि व्यवस्था के अनुसार ओ.सी./सी.सी. मिलने अथवा कब्जा ऑफर किये जाने, जो भी बाद में हो की तिथि तक शिकायतकर्ता विलम्ब ब्याज पाने का अधिकारी होगा। ऐसी दशा में शिकायतकर्ता ओ.सी., सी.सी. मिलने अथवा कब्जा ऑफर किये जाने, जो भी बाद में हो तक की अवधि तक विलम्ब के लिए ब्याज पाने के अधिकारी होगें । दिनांक (7.020i8 को उ0प्र० शासन आवास एवं शहरी नियोजन अनुभाग-3 की अधिसूचना संख्या-4740 /8-3-8-65 विविध / 46 के द्वारा मॉडल एग्रीमेन्ट की नियमावली के प्रस्तर-7 में फोर्स मैज्योर के सम्बन्ध में निम्न उल्लेख किया गया है:- 7. POSSESSION OF THE APARTMENT/PLOT: {V Page SS Page? —— े-------आणक्म माय मननम न
"य्.] Schedule for possession of the said [Apartment/Plot] - The Promoter agrees and understands that timely delivery of possession of the [Apartment/Plot] to the Allottee and the Common Areas to the association of Allottees or the competent authority, as the case may be, is the essence of the Agreement. The Promoter assures to hand over possession of the [Apartment/Plot] along with ready and complete Common Areas with all specifications, amenities and facilities of the Project in place on , unless there is delay or failure due to war, flood, drought, fire, cyclone, earthquake or any other calamity caused by nature affecting the regular development of the real estate project ("Force Majeure"). If, however, the completion of the Project is delayed due to the Force Majeure conditions then the Allottee agrees that the Promoter shall be entitled to the extension of time for delivery of possession of the [Apartment/Plot]:" इसी क्रम में समस्त सुसंगत तथ्यों एवं परिस्थितियों के बाद उ0प्र0 रेरा अथॉरिटी द्वारा कोविड-49 (Corona Virus Disease) के प्रभाव के कारण सभी परियोजनाओं को पूर्ण करने हेतु दिनाक 25.03.2020 से 6 माह की अवधि * अर्थात् दिनांक 25.09.2020 तक की अवधि दे दी गयी है और यह अवधि फोर्स मैज्योर की अवधि मानी जायेगी। इसको दृष्टिगत रखते हुए दिनांक 25.03.2020 से दिनांक 25.09.2020 तक परियोजना में हुए विलम्ब हेतु कोई ब्याज प्रोमोटर द्वारा आवंटियों को नहीं दिया जाएगा और न ही आवंटियों से कोई विलम्ब ब्याज लिया जायेगा। तदनुसार बिन्दु संख्या-3 Peake किया जाता है।
उपरोक्त बिन्दुओं का निस्तारण करते हुए निम्न आदेश पारित किये जाते हैं :- आदेश “4. विपक्षी को आदेशित किया जाता है कि वह शिकायतकर्तागण के यूनिट्स की समस्त सुविधाओं को आवंटन--पत्र / अनुबन्ध के अनुसार पूर्ण कराकर दिनांक 30.09.202 तक ओ-सी./ सी.सी. सहित कब्जा देना सुनिश्चित करें और देय स्टाम्प शुल्क प्राप्त कर नियमानुसार रजिस्ट्री करायें। 7 oe e_ooraesoaeer Page 8 8 2... विपक्षी, शिकायतकर्ता को दिनांक 24.42.2046 से ओ.सी /सी.सी प्राप्त होने अथवा कब्जा ऑफर किये जाने, जो भी बाद में हो, की तिथि तक शिकायतकर्ता द्वारा जमा धनराशि पर MCLR+I प्रतिशत की दर से विलम्बित अवधि का ब्याज अदा करना सुनिश्चित करें। साथ ही यह भी स्पष्ट किया जाता है कि ब्याज की यह धनराशि अंतिम भुगतान की धनराशि में समायोजित की जायेगी और यदि ब्याज की धनराशि देय धनराशि से अधिक है, तो नियमानुसार शिकायतकर्ता को वापस की जाये। कोविड-49 की रोकथाम एवं नियंत्रण हेतु देश में हुए लॉकडाउन एवं फोर्स मैज्योर को दृष्टिगत रखते हुए दिनांक 25.03.2020 से दिनांक 25.09.2020 तक परियोजना में हुए विलम्ब हेतु ब्याज की गणना नहीं की जाएगी। 3. विपक्षी, उपरोक्तानुसार कब्जा ऑफर पत्र ओ.सी. मिलने के उपरान्त जारी करना सुनिश्चित करें। 4. विपक्षी को निर्देशित किया जाता है कि रेरा अधिनियम 2046 के धारा 2 (००)0) के अन्तर्गत ब्याज को परिभाषित किया गया है कि रेरा लागू होने के बाद यदि कोई ब्याज दर आवंटी के डिफॉल्ट से प्रोमोटर द्वारा लिया जा है, तो उसी दर से ब्याज प्रोमोटर द्वारा डिफॉल्ट किये जाने पर भी आवंटी को दिया जायेगा। राज्य सरकार द्वारा अधिसूचित ब्याज दर ४(१,२+। प्रतिशत है।
इस आदेश का उल्लघंन भू-सम्पदा (विनियमन एवं विकास) अधिनियम, 2046 की धारा-63 तथा अन्य सुसंगत प्राविधानों के अन्तर्गत दंडनीय होगा। आदेश पोर्टल पर अपलोड किया जाये। दिनांक +- 09/07 / 2024 RUZ ( | | 5 ( BAR) (सदस्य) उ0प्र0 भू-सम्पदा विनियामक प्राधिकरण