Uttar Pradesh Real Estate Regulatory Authority
Rachana Sharma and Rajesh Kumar Sinha v. Logix Infra Developers Pvt.ltd
Complaint No. NCR144/09/61897/2020
- Decision date
- 2021-07-19
- Text availability
- Machine-read (OCR) text, unverified
- Bench
- Adjudicating Officer Gautam Budh Nagar
Source: UP RERA order
Connected provisions and cases
No further provision or case links are recorded.
Judgment text
उ0प्र0 भू-सम्पदा विनियामक प्राधिकरण, क्षेत्रीय कार्यालय, गौतमबुद्धनगर। सुनवाई पीठ-04ए E-Court श्री राजीव कुमार, माननीय अध्यक्ष कम शिकायत संख्या शिकायतकर्तागण् | af संख्या संख्या i a I | NCR44/I0/62437/2020 | सुरेन्दर सिंह धीर एवं यशवन्त | F-703 कौर धीर 2 NCRI44/09/6897/2020 | रचना शर्मा एवं राजेश कुमार | 0 सिन्हा i बनाम मैसर्स लॉजिक्स sear डेवलपर्स yo fo शिकायतकर्ता सुरेन्दर सिंह धीर एवं यशवन्त कौर dk के साथ 4 अन्य शिकायतकर्ता द्वारा विपक्षी के विरूद्ध वाद योजित किये गये हैं। इन दोनों शिकायतों के तथ्य समान है और एक समान साक्ष्य हैं। यह दोनों शिकायतें Neoworld Phase-I से सम्बन्धित है। अतः एक ही निर्णय से इनका निस्तारण किया जा रहा है। शिकायत संख्या : ॥९८7९44/0/62437/2020 सुरेन्दर सिंह de एवं यशवन्त कौर धीर अग्रणी वाद रहेगा। प्रस्तुत प्रार्थना पत्र शिकायत्कर्तागण द्वारा विपक्षी के विरूद्द कब्णा एवं विलम्बित अवधि का ब्याज दिलाये जाने हेतु संस्थित किया गया है। संक्षेप में शिकायतकर्ता का कथन है कि शिकायतकर्ता द्वारा में विपक्षी की परियोजना Neoworld Phase-l के टॉवर-7 में फ्लैट संख्या-703 बुक कराया गया था, जिसके लिए शिकायतकर्ता द्वारा समय-समय पर किश्तों के आधार पर a 2
43,78,395/— रुपये का भुगतान किया गया। पक्षकारों के मध्य दिनांक 26.03.202 को अनुबन्ध निष्पादित कराया गया, जिसके अनुसार विपक्षी द्वारा शिकायतकर्ता को दिनांक 26.05.2045 तक परियोजना पूर्ण कर कब्जा दिये जाने का दायित्व था, परन्तु विपक्षी द्वारा उक्त निर्धारित अवधि तक कब्जा नहीं दिया गया और विपक्षी की परियाजना लगभग 5 वर्ष 4 माह विलम्बित है। अतः शिकायतकर्ता द्वारा कब्जा एवं विलम्बित अवधि का ब्याज दिलाये जाने का अनुरोध किया गया है। शिकायतकर्ता की ओर से अपने कथन के समर्थन में फ्लैट केता अनुबन्ध दिनांक 26.03.2042, जमा धनराशि की रसीदों की छायाप्रतियाँ दाखिल की गयी है। विपक्षी द्वारा प्रतिवादपत्र दिनांकित 27.:2.2020 दाखिल करते हुए कहा गया है कि शिकायतकर्ता द्वारा विधि का दुरूपयोग करते हुए वाद योजित किया गया है। परियोजना फोर्स मैज्योर इवेन्टस् के कारण विलम्बित हुई, जो कि उनके नियंत्रण में नहीं था। दिल्ली ४८९४ में बढ़ते हुए प्रदूषण को ध्यान में रखते हुए माननीय सर्वोच्च न्यायालय द्वारा दिनांक 04.44.2049 को निर्माण कार्य पर रोक लगा दी गयी थी। परियोजना में निर्माण कार्य, कोविड-49 के फैलने के कारण भी विलम्ब हुआ है। शिकायतकर्ता द्वारा दिनांक 49.42.2044 को उनकी परियोजना के टॉवर-# में यूनिट संख्या-703 बुक करायी गयी। अनुबन्ध रेरा लागू होने से पूर्व निष्पादित कराया गया है। उभयपक्ष के तर्कों को सुना गया व पत्रावली का अवलोकन किया गया, जिसके आधार पर निम्नलिखित वाद बिन्दु विचरित किये गये :- 4... क्या रेरा आने से पूर्व के अनुबन्ध ta के दायरे में नहीं आते हैं ? व क्या पक्षकारों के मध्य रेरा लागू होने से पूर्व अनुबन्ध निष्पादित किये जाने पर रेरा के प्राविधान लागू नहीं होगें ?
2. क्या force majeure events होने के कारण विपक्षी की परियोजना विलंबित हुई? यदि हां तो प्रभाव? 3. क्या शिकायतकर्तागण को कब्जा एवं विलम्बित अवधि का ब्याज दिलाया जाये? यदि हाँ तो ब्याज की क्या दर होगी ? ? निस्तारण बिन्दु संख्या-4 बिन्दु संख्या । इस तथ्य पर विचरित है कि क्या रेरा आने से पूर्व के अनुबन्ध रेरा के दायरे में नहीं आते है? व क्या पक्षकारों के मध्य रेरा लागू होने से पूर्व अनुबन्ध निष्पादित किये जाने पर रेरा के प्राविधान लागू नहीं होगें ? इस सम्बन्ध में बॉम्बे उच्च न्यायालय द्वारा Re याचिका संख्या-2737 / 2047 “नीलकमल रियलटर्स सबअर्बन प्राणलि0 एवं अन्य बनाम यूनियन ऑफ इंडिया” 4 fear गया आब्जर्वेशन महत्वपूर्ण है जिसमें स्पष्ट रूप से उल्लिखित किया गया है कि :- | 86. On behalf of the petitioners it was submitted that registration of ongoing project under RERA would be contrary to the contractual rights established between the promoter and allottee under the agreement for sale executed prior to registration under RERA. In that sense, the provisions have retrospective or retroactive application. After assessing, we find that the projects already completed are not in any way affected and, therefore, no vested or accrued rights are getting affected by RERA. The RERA will apply after getting the project registered. In that sense, the application of RERA is prospective in nature.
87. The important provisions like Section 3 to 9, 40, 59 to 70 and 79 to 80 were notified for operation from /5/207. RERA law was enacted in the year 20l6. The Central Government did not make any haste to implement these provisions at one and the same time, but the provisions were made applicable thoughtfully and phase-wise. Considering the scheme of RERA, object and purpose for which it is enacted in the larger public interest, we do not find that challenge on the ground that it violates rights of the petitioners under Articles 4 and 9(l)(g) stand to reason. Merely because sale and purchase agreement was entered into by the promoter prior to coming into force of RERA does not make the application of enactment retrospective in nature. The RERA was passed because it was felt that several promoters had defaulted and such defaults had taken place prior to coming into force of pt RERA. In the affidavit-in- reply, the UOI had stated that in the State of Maharashtra [2608 ongoing projects have been registered, while 806 new projects have been registered. This figure itself would justify the registration of ongoing projects for regulating the development work of such projects.
89. Legislative power to make law with retrospective effect is well recognized. In the facts, it would not he permissible for the petitioners to os-wp-2737-l7 & ors-RERA-JT.doc say that they have vested right in dealing with the completion of the project by leaving the proposed allottees in helpless and miserable condition. In a country like ours, when millions are in search of homes and had to put entire life earnings to purchase a residential house for them, it was compelling obligation on the Government to look into the issues in the larger public interest and if required, make stringent laws regulating such sectors. We cannot foresee a situation where helpless allottees had to approach various forums in search of some reliefs here and there and wait for the outcome of the same for indefinite period. The public interest at large is one of the relevant consideration in determining the constitutional validity of retrospective legislation.
256. "Section 4(2)(l)(C) enables the promoter to revise the date of completion of project and hand over possession. The provisions of RERA, however, do not rewrite the clause of completion or handing over possession in agreement for sale. Section 4(2)(I)(C) enables the promoter to give fresh time line independent of the time period stipulated in the agreements for sale entered into between him and the allottees so that he is not visited with penal consequences laid down under RERA. In other words, by giving opportunity to the promoter to prescribe fresh time line under Section 4(2)0)(0) he is not absolved of the liability under the agreement for sale." उपरोक्त विधि व्यवस्था से यह स्पष्ट है कि रेरा के प्राविधान के अनुसार अनुबन्ध में दिये गये पूर्णता एवं कब्जे देने के We का पुनर्लेखन नहीं किया जा सकता। धारा 4(2)0)(सी) के अन्तर्गत प्रोमोटर एक नई समय सीमा दे सकता है, जो
कि अनुबन्ध पर निर्भर नहीं होगा और vat धारा रेरा में दिये गये प्राविधान के परिणाम स्वरूप केवल अर्थदंड से बचाया जा सकता है। अतः इससे अवधारित किया जाता है कि प्रोमोटर अनुबन्ध में दिये गये कब्जे की तिथि के लिए उत्तरदायी है। यह भी रेरा अधिनियम में स्पष्ट है कि “ऑन गोईंग” परियोजनायें निश्चित रूप से रेरा अधिनियम की परिधि में आते है। उपरोक्त माननीय उच्च न्यायालय के आर्ब्जवेशन से यह भी स्पष्ट है कि यद्यपि रेरा पंजीकरण से पूर्व प्रोमोटर एवं आवंटी के मध्य अनुबन्ध निष्पादित हुए हैं, परन्तु यदि परियोजना को रेरा में पंजीकरण कराया जात्ता है, तो रेरा के सभी प्राविधान लागू होगें। we है कि प्रश्नगत परियोजना को रेरा में पंजीकृत कराया गया है और यह ऑनगोई की श्रेणी में है। ऐसी दशा में रेरा के सभी प्राविधान लागू होगें। तद्नुसार बिन्दु dea-i निस्तारित किया जाता है। निस्तारण बिन्दु संख्या-2 बिन्दु संख्या-2 इस आशय का विचरित किया गया है कि क्या वास्तव में परियोजना फोर्स मैज्योर इवेन्टस होने कारण विलम्बित हुई ? यह बिन्दु विपक्षी के अभिकथनों पर विचरित किया गया है, जिसे साबित करने का भार विपक्षी पर है। विपक्षी की ओर से कथन किया गया है कि परियोजना फोर्स मैज्योर इवेन्टस् के कारण विलम्बित हुई, जो कि उनके नियंत्रण में नहीं था। दिल्ली NCR F बढ़ते हुए प्रदूषण को ध्यान में रखते हुए माननीय सर्वोच्च न्यायांलय द्वारा दिनांक 04.2. 20i9 को निर्माण कार्य पर रोक लगा दी गयी थी। परियोजना में निर्माण कार्य, कोविड-49 के फैलने के कारण भी विलम्ब हुआ है। इस सम्बन्ध में फ्लैट Sa अनुबन्ध के प्रस्तर-6.2 निम्नलिखिल vectra a
6.2 The Parties agree and acknowledge that where the completion of the construction of the Apartment and/or the handing over of the possession of the Apartment is delayed by any reasons beyond the control of the Company, including witout limitation Force Majeure (defined hereinafter), then no claim whatsoever by way of any damages/compensation shall be raised against the Company, and the Buyer hereby waives all rights and claims in this regard. Further, where any delay occurs in possession being handed over to the Buyer on account of YJ any of the reasons specified under this Clause 6.2, the Company shall be entitled to a reasonable extension of time of handing over possession of the said Apartment to the Buyer. For the purpose of this Agreement "Force Majeure" shall mean any event or circumstances or a combination of events and circumstances, whether occured or likely to occur, which satisfies all the follwing conditions: i) Materially and adversely affects the Project and/or the performance of an obligation of the Company; and ii) Are beyond the control of the Company; and includes (without limitation), subject to satisfaction of the above conditions, the following events and/or circumstances: a) war (whether declared or undeclared), invasion, armed conflict or act of foreign enemy; b) revolution, riot, insurrection or other civil commotion, act of terrorism or sabotage;
22 strikes, industrial disputes, and/or lockouts and/or interrupting supplies and services to the Project. da) change in govermental policy, laws (including any statute, ordinance, rule, regulation, judgment, notification, order, decree, permission, licence or approval), including but not limited to expropriation or compulsory acquisition by any Government of any part of the Project or rights therein; e) acts of God or events beyond the reasonable control of the affected party which could not reasonably have been expected, including any effect of the natural elements, including lighting, fire, earthquake, unprecedented rains, landslide, subsidence, flood, storm, cyclone, epidemics or plagues or any other similar effect; J) any judgement or order of any court of competent jurisdiction or Government in India made against the Company in any proceedings. >>) इस सम्बंध में माननीय एन.सी.डी.आर.सी द्वारा उपभोक्ता शिकायत संख्या-4430 /20i6 “ Are कौशल एवं अन्य बनाम यूनिटेक लिमिटेड” में निर्णय के Ter 44 में फोर्स मैज्योर द्वारा परियोजना विलम्बित होने के लिए निम्न ऑबजरवेशन किया है :-
"Coming to the plea of Force Majeure taken by the opposite party. It may be noted that issue raised by the opposite party is no more resintegra. Similar pleas to explain the delay in construction were taken by the opposite party in Consumer Complaint No.347 of 294 Swarn Talwar and 2 Ors. Vs. Unitech Ltd. and other connected consumer complaints which pertain to the alleged deficiency i.e. failure of the opposite party to deliver possession of the booked apartments in the same project. In the aforesaid matters, Coordinate Bench of this Commission vide order dated 4.08.20I5 declined to accept the plea of Force Majeure taken by the opposite party. The relevant reasoning of the Coordinate Bench rejecting the plea of Force Majeure is reproduced as under: "Coming to the pleas that there was recession in the economy and a disruption due to agitation by farmers and acute shortage of labour, etc., the following view taken by us In Satish Kumar Pandey (Supra) is relevant.
"Neither any new legislation was enacted nor an existing rule, regulation or order was amended stopping suspending or delaying the construction of the complex in which apartments were agreed to be sold to the complainants. There is no allegation of any lock- out or strike by the labour at the site of the project. There is no allegation of any slow-down having been resorted to by the labourers of the opposite party or the contractors engaged by it at the site of the project. There was no civil commotion, war, enemy action, terrorist action, earthquake or any act of God which could have delayed the completion of the project within the time stipulated in the Buyers Agreement. It was contended by the counsel for the OP that the expression 'slow down' would include economic slow- down or recession in the Real Estate sector. I, ol however, find no merit in this contention. The word ‘slow down' having been used alongwith the words lock-out and strike, I has to be read ejusdem generis with the words lock-out and strike and therefore, can mean only a slow down if resorted by the labourers engaged in construction of the project." माननीय सर्वोच्च न्यायालय द्वारा सिविल अपील संख्या-43029 / 4985 “एम. सी. मेहता बनाम भारत सरकार” में पारित आदेश दिनांक 04.4.2049 में निम्नलिखित निर्देश दिये है :-
With respect to demolition and construction activities we direct that no demolition and construction activities take place in Delhi and NCR region. In case it is found that such activity is done, the local administration as well as the municipal authorities including the Zonal Commissioners, Deputy Zonal Commissioners shall be personally held responsible for all such activities. They have to act in furtherance of the Court’s order and to ensure that no such activity takes place. We direct that consiruction, demolition and activities be stopped forthwith as well as garbage burning. In case, any person is found in construction and demolition activity and garbage burning in Delhi and NCR region, he/she shall be penalized. Any person is doing construction and demolition activity in violation of this order, shall be penalized with Rs.l Lac for such activity. For garbage burning he/she shall be penalized with Rs.5,000/- and besides liable for violation of the order passed by this Court to be dealt with in accordance with law. इसके अतिरिक्त उपरोक्त सिविल अपील संख्या-43029 / 4985 में पारित आदेश दिनांक 09.42.2049 में निम्नलिखित निर्देश दिये है :- In the affidavit dated 05.2.209, the Central Pollution Control Board (CPCB) has stated as under:- "]2, That it is respectfully submitted that it is normally experienced that in month of December depending upon Climatic Condition the AQI category varies. As a matter py
of fact, last year (208) 8 days in the month of December were in severe AQI category. Presently the situation not being severe, CPCB is of considered opinion that partial ban could be in place of construction activities in as much as no construction should be permitted during night time (6.00 pm to 6.00 am). The ban imposed could be partially lifted by permitting activities during day time (6.00 am to 6.00 pm), subject to the criteria stipulated in GRAP, wherein strict emforcement of rules for dust control in construction activities and closure of non-compliant sites is mandated in moderate to poor AQI category and further a bank on construction activities may be imposed by EPCA if Ambient AIR quality levels persist in severe+/emergency category for 48 hours or more." Hence, the ban is relaxed in terms of the recommendations made by Central Pollution Control Board (CPCB), as quoted above. However, conditions for raising construction be scrupulously followed. इसके अतिरिक्त माननीय उच्चतम न्यायालय द्वारा सिविल अपील संख्या-940 /20:7 “विकम चटर्जी एवं अन्य बनाम यूनियन ऑफ इंडिया एवं अन्य” में निर्णय के पृष्ठ संख्या-234 एवं प्रस्तर 440 में फोर्स मैज्योर को निम्नवत् परिभाषित किया है:- "006 majeure shall mean a case of war, flood, drought, fire, cyclone, earthquake or any other calamity caused by nature."
उपरोक्त फोर्स मैज्योर के परिभाषा से यह स्पष्ट है कि फोर्स मैज्योर वह स्थिति है, जिसमें की युद्ध, बाढ़, सूखा, आग, तूफान, भूकम्प या अन्य प्रकृतिक आपदा आई हो, प्रश्नगत प्रकरण में ऐसी कोई परिस्थिति उत्पन्न नहीं हुई। माननीय सर्वोच्च न्यायालय द्वारा (दिनांक 04.::.20i9 से दिनांक 44.02.2020) की अवधि के लिए निर्माण कार्य पर रोक लगायी गयी है, जिसमें माननीय सर्वोच्च न्यायालय द्वारा पारित आदेश दिनांक 09.2.2049 में पूर्ण प्रतिबन्ध को हटाते हुए आंशिक प्रतिबन्ध लगाया गया। ऐसे में माननीय सर्वोच्च न्यायालय द्वारा 35 दिन (दिनांक 04.::20I9 से दिनांक 09.42.2049) एवं 33 दिन (6652) (दिनांक 40.2.2049 से दिनांक 24.02. 2020 तक Uae बजे से सुबह 6 बजे तक) की अवधि के लिए निर्माण कार्य पर प्रतिबन्ध लगाया गया। अतः उपरोक्त उल्लेखित आदेशों के कम में कुल 68 दिनों में py 0 निर्माण प्रभावित vet! विपक्षी ऐसी दशा में कुल 68 दिन निर्माण कार्य प्रभावित रहने के कारण लाभ पाने का अधिकारी है। दिनांक 47.0.2048 को BOW शासन आवास एवं शहरी नियोजन अनुभाग-3 की अधिसूचना संख्या-4740/8-3-48-65 विविध /ie के द्वारा मॉडल एग्रीमेन्ट के प्रस्तर-7 में फोर्स मैज्योर के सम्बन्ध में निम्न उल्लेख किया गया है :- 7. POSSESSION OF THE APARTMENT/PLOT:
"7, | Schedule for possession of the said [Apartment/Plot] - The Promoter agrees and understands that timely delivery of possession of the [Apartment/Plot] to the Allottee and the Common Areas to the association of Allottees or the competent authority, as the case may be, is the essence of the Agreement. The Promoter assures to hand over possession of the [Apartment/Plot] along with ready and complete Common Areas with all specifications, amenities and facilities of the Project in place on न unless there is delay or failure due to war, flood, drought, fire, cyclone, earthquake or any other calamity caused by nature affecting the regular development of the real estate project ("Force Majeure"). If, however, the completion of the Project is delayed due to the Force Majeure conditions then the Allottee agrees that the Promoter shall be entitled to the extension of time for delivery of possession of the [Apartment/Plot]:"
इस कम में समस्त सुसंगत तथ्यों पर विचारोपरान्त wooo रेरा अथॉरिटी द्वारा दिनांक 20.05.2020 को कोविड-49 (Corona Virus Disease) के प्रभाव के कारण सभी परियोजनाओं को पूर्ण करने हेतु दिनांक 25.03.2020 से 6 माह की अवधि अर्थात् दिनांक 25.09.2020 तक की अवधि दे दी गयी है और यह अतिरिक्त अवधि फोर्स मैज्योर इवेन्टस् के कारण मानी जायेगी। इसको दृष्टिगत रखते हुए दिनांक 25.03.2020 से दिनांक 25.09.2020 तक परियोजना में हुए विलम्ब हेतु कोई ब्याज प्रोमोटर द्वारा आवंटियों को नहीं दिया जाएगा और न ही शिकायतकर्ता से अतिदेय धनराशि पर कोई विलम्ब ब्याज लिया जायेगा। तद्नुसार बिन्दु संख्या-2 निस्तारित किया जाता है। yf 42 निस्तारण बिन्दु संख्या-3 शिकायतकर्ता का कहना है कि पक्षकारों के मध्य दिनांक 26.03.2042 को अनुबन्ध निष्पादित कराया गया, जिसके अनुसार विपक्षी द्वारा शिकायतकर्ता को दिनांक 26.05.2045 तक परियोजना पूर्ण कर कब्जा दिये जाने का दायित्व था, परन्तु विपक्षी द्वारा उक्त निर्धारित अवधि तक कब्जा नहीं दिया गया और विपक्षी की परियाजना लगभग 5 वर्ष 4 माह विलम्बित है। अत: शिकायतकर्ता द्वारा कब्जा एवं विलम्बित अवधि का ब्याज दिलाये जाने का अनुरोध किया गया है। इस पर विपक्षी द्वारा दाखिल प्रतिवाद पत्र में कब्जा दिये जाने के सम्बन्ध में कोई समयावधि अंकित नहीं की गयी है। रेरा एक्ट की धारा 8 (॥) में प्राविधान है कि :- Section 726 (2 “If the promoter fails to complete or is unable to give possession of an apartment, plot or building,- (a) in accordance with the terms of the agreement for sale or, as the case may be, duly completed by the date specified therein; or
(b) due to discontinuance of his business as a developer on account of suspension or revocation of the registration under this Act or for any other reason, he shall be liable on demand to the allottees, in case the allottee wishes to withdraw from the project, without prejudice to any other remedy available, to return the amount received by him in respect of that apartment, plot, building, as the case may be, with interest at such rate as may be prescribed in this behalf including compensation in the manner as provided under this Act: Provided that where an allottee does not intend to withdraw from the project, he shall be paid, by the promoter, interest for every month of delay, till the handing over of the possession, at such rate as may be prescribed. इस प्रकार केता को यह अधिकार है कि यदि उन्हें एग्रीमेंट के अनुरूप कब्जा नही मिलता तो वह अपनी जमा धनराशि को ब्याज सहित वापिस माँग सकते हैं अथवा प्रत्येक माह के विलम्ब के लिए ब्याज प्राप्त करते हुए परियोजना में बने रहें। १ १2 प्रश्नगत प्रकरणों में शिकायतकर्तागण द्वारा कब्जा एवं विलम्बित अवधि का ब्याज दिलाये जाने का अनुरोध किया गया है। पत्रावली पर शिकायतकर्ता द्वारा फ्लैट dat अनुबन्ध दिनांक 26.03.2042 की छायाप्रति दाखिल की गयी है, जिसके प्रस्तर-6.4 निम्नलिखित उल्लेखित है :-
५......॥6७ Company shall endeavor to complete the construction of the Apartment within 30 months from the date of the execution of this agrecment. After the expiry of the aforesaid 30 months, the company shall have a grace period of 6 (Six) months for the Apartment situated in Towers Al, BI, 82, DI, D2, N3, D4 and a period of 8 (Eight) months to complete the construction of the Apartment situated in Towers B3, Cl, C2, C3, D5, D6 ("Grace Period")." इस सम्बन्ध में फ्लैट केता अनुबन्ध दिनांक 2603.20i2 के प्रस्तर-6.6 निम्नलिखित उल्लेखित है :- conse in the event of any wilful delay in construction of the Apartment beyond the grace period, for reasons attributable solely to the Company, delay charges would be payable to the Buyer at the rate of Rs.5 per Sq. Ft. per month on super area for each completed month of delay calculated from the date of expiry of the Grace Period. शिकायतकर्ता की यूनिट परियोजना के टॉवर-एफ में है, जिसका कब्जा उपरोक्तानुसार अनुबन्ध निष्पादित किये जाने की तिथि रो i8 माह में कब्जा दिया जाना था। फ्लैट केता अनुबन्ध दिनांक 26.03.20i2 को निष्पादित किया गया एवं अनुबन्ध के AR 6 के अनुसार विपक्षी द्वारा दिनांक 26.09.203 तक कब्जा देना था, किन्तु विपक्षी द्वारा निर्धारित अवधि में कब्जा नहीं दिया गया है। इसके अतिरिक्त फोर्स मैज्योर के मद में विपक्षी कुल 68 दिन की अवधि के लिए लाभ पाने का अधिकारी है। (जैसा कि निस्तारण बिन्दु संख्या-2 में वर्णित है।)
जहाँ तक किस अवधि तक का ब्याज दिलाये जाने का प्रश्न है। इस सम्बन्ध में सिविल अपील Ho 6649-50 ,/2048 "सुपरटेक लिमिटेड बनाम रजनी गोयल" में माननीय उच्चतम न्यायालय द्वारा अभिनिर्धारित किया गया है कि:- "the period of Interest should close on April 206 when the Full Occupancy Certificate was obtained as per the ps 433 admission of the Respondent - Purchaser herself in Para 4(j) of the Consumer Complaint, wherein she has admitted that the Appellant —Builder had obtained the Completion Certificate as late as April 20I6. The Respondent - Purchaser could not have any further grievance after April 206 with respect to delay in handing over possession. The Respondent — Purchaser ought not to be allowed to reap the benefits of her own delay in taking possession. " उपरोक्त विधि व्यवस्था के अनुसार ओ.सी.,/सी.सी. अथवा कब्जा ऑफर किये जाने की तिथि, जो भी बाद में हो तक शिकायतकर्ता विलम्ब ब्याज पाने का अधिकारी होगा। ऐसी दशा में शिकायतकर्ता को दिनांक 26.09.203 + 68 दिन अर्थात् 03.2.203 से ओ.सी /सी.सी अथवा कब्जा ऑफर किये जाने की तिथि, जो भी बाद में हो तक विलम्बित अवधि का ब्याज दिलाया जाना न्यायोचित प्रतीत होता है। जहाँ तक ब्याज देयता का प्रश्न है। माननीय बॉम्बे उच्च न्यायालय द्वारा “नीलकमल रियलटर्स सबअर्बन प्रा.लि. आदि बनाम यूनियन ऑफ इंडिया” के वाद में अभिनिर्धारित किया गया है कि :-
"Section 8()(0) lays down that if the promoter fails to complete or is unable to give possession of an aprtment due to discontinuance of his business as a developer on account of suspension or revocation of the registration under the Act or for any other reason, he is liable on demand to the allottees, in case the allottee wishes to withdraw from the project, without prejudice in this behalf including compensation. If the allottee does not intent to withdraw from the project he shall be paid by the promoter interest for every month's delay till handing over of the possession,. The requirement to pay interest is not a penalty as the payment of interest is compensatory in nature in the light of the delay suffered by the allottee who has paid for his apartment but has not received possession of it. The obligation imposed on the promoter to pay interest till such time as the apartment is handed over to him is not unreasonable. " ०) 44 अत: उपरोक्त निर्णय के आलोक में यह स्पष्ट है कि उ0प्र0 रेरा के प्राविधानों के अन्तर्गत प्रमोटर व केता के बीच किये गये अनुबंध के अनुरूप विलम्ब तथा मूल धनराशि पर ब्याज देय होगा, क्योंकि प्रमोटर्स द्वारा उक्त धनराशि का उपभोग किया गया है।
यह भी उल्लेखनीय है कि पक्षकारों के मध्य एक अनुबन्ध निष्पादित है, जो कि उभयपक्ष द्वारा हस्ताक्षरित है, जिससे यह अवधारित किया जा सकता है कि उभयपक्ष को उक्त अनुबन्ध की शर्ते स्वीकार हैं। अनुबन्ध के प्रस्तर-6.6 के अनुसार परियोजना के विलंब की अवधि में 5,/- रूपये प्रतिवर्ग फुट प्रतिमाह की दर से धनराशि का प्राविधान है, जिसके अनुसार शिकायतकर्ता धनराशि पाने का अधिकारी है, रेरा के प्राविधानों के अनुसार जिस दर से विपक्षी द्वारा धनराशि प्राप्त की गयी है उसी दर से धनराशि देने का प्राविधान है। इस सम्बन्ध में भू-सम्पदा (विनियमन एवं विकास) अधिनियम, 20:6 aT vada दिनांक 04.05.2047 को हुआ, जिसके सम्बन्ध में उ0प्र० आवास एवं शहरी नियोजन अनुभाग-2 की अधिसूचना दिनांक 03.05.20:7 से उ0प्र0 में रेगुलेटरी अथॉरिटी के रूप मे कार्य करने की स्वीकृति राज्यपाल, महोदय ने दिनांक 04.05.2047 से प्रदान की अर्थात् दिनांक 04.05.2047 से भू-सम्पदा (विनियमन एवं विकास) अधिनियम, 206 का प्रवर्तन उ0प्र0 में प्रारम्भ हुआ अर्थात् उ0प्र0 में यह अधिनियम दिनांक 0.05.2047 से लागू हुआ है। इस अधिनियम का प्रवर्तन प्रोस्पेक्टिव है। अतः दिनांक 04.05.2047 से पूर्व की अवधि के लिए विलम्ब ब्याज की गणना अनुबन्ध के प्रावधानों के अन्तर्गत की जायेगी और दिनांक 0.05. 2047 से आगे की अवधि के लिए विलम्ब ब्याज की गणना अधिनियम के प्रावधानों के अन्तर्गत की जायेगी।
जहाँ तक देय ब्याज दर का प्रश्न है, तो राज्य सरकार द्वारा भू-सम्पदा (विनियमन एवं विकास) अधिनियम 20i6 के अधीन दिनांक 7.0.20:8 को भू-सम्पदा (विनियमन और विकास) (विकय,/पटटा के लिए करार) नियमावली 20:8 अधिसूचित की गयी हैं। इसमें संलग्नक के रूप में दिये गये विकय,/पटटा विलेख के प्रारूप के प्रस्तर 9 में प्रमोटर्स के डिफाल्ट प्रकरण Events of default) परिभाषित है, जिसमें प्रस्तर 9.20) में प्रमोटर के डिफाल्टर होने की स्थिति में आवंटी हेतु प्राविधानित है कि:- "The Allottee shall have the option of terminating the Agreement in which ease the Promoter shall be liable to refund the entire money paid by the Allottee under any head whatsoever towards the purchase of the apartment, along with interest at the rate equal to MCLR (Marginal Cost of Lending Rate) on home loan of State Bank of India + % unless provided otherwise ¥ 45 under the Rules. within forty-five days of receiving the termination notice:" यही दर आवंटियों के द्वारा डिफॉल्ट की स्थिति में भी प्रस्तर 9.30) में निर्धारित है। wat प्राविधान को दृष्टिगत रखते हुए आवंटी को MCLR+I प्रतिशत की ब्याज दर पर विलम्बित अवधि का ब्याज दिलाया जाना न्यायोचित प्रतीत होता है। यह भी स्पष्ट किया जाता है कि यदि शिकायतकर्ता की कोई धनराशि अतिदेय है, तो उस पर विपक्षी भी McLR+ प्रतिशत की दर से ही ब्याज प्राप्त कर सकता है। रेरा की धारा-2(28)0) में भी यही ब्याज की परिभाषा दी गयी है। तद्नुसार बिन्दु संख्या-3 PraRa किया जाता है। उपरोक्त बिन्दुओं का निस्तारण करते हुए निम्न आदेश पारित किये जाते है। आदेश
l. विपक्षी को आदेशित किया जाता है कि वह शिकायतकर्तागण के फ्लैट्स की समस्त सुविधाओं को अनुबन्ध के अनुसार पूर्ण कराकर दिनांक 30.09.202 तक ओ.सी,/सी.सी सहित कब्जा देना सुनिश्चित करें और देय स्टाम्प शुल्क प्राप्त कर नियमानुसार रजिस्ट्री कराना सुनिश्चित करें। 2. विपक्षी, शिकायतकर्ता को 03.42.2043 से दिनांक 30.04.2047 तक 5/- रूपये प्रति वर्ग we प्रतिमाह की दर से व दिनांक 04.05.2047 से ओ.सी. /सी.सी. अथवा कब्जा ऑफर किये जाने की तिथि, vit भी बाद में हो, तक की अवधि ux शिकायतकर्ता द्वारा जमा धनराशि पर विलम्ब ब्याज के रूप में MCLR+I प्रतिशत ब्याज अदा करना सुनिश्चित करें| ब्याज की यह धनराशि अंतिम भुगतान की देय धनराशि में समायोजित की जायेगी। ब्याज की धनराशि देय धनराशि से अधिक होने पर शिकायतकर्ता को वापस की जायेगी। फोर्स मैज्योर पीरियड को दृष्टिगत रखते हुए दिनांक 25.03.2020 से दिनांक 25.09.2020 तक परियोजना में हुए विलम्ब हेतु ब्याज की गणना नहीं की जायेगी। साथ ही इस अवधि में शिकायतकर्ता द्वारा यदि कोई होल्डिंग चार्जेज़ अनुबन्धानुसार देय न होगा तथा यदि कोई अतिदेय (Over Dues) है, तो उस पर भी इस अवधि का ब्याज देय न होगा। अन्य शिकायतकर्ता के प्रकरण में अनुबन्ध के अनुरूप उपरोक्तानुसार गणना की जायेगी। Vv 46
विपक्षी को यह निर्देशित किया जाता है कि रेरा अधिनियम, 2046 की धारा 2(2०)0) के अनुसार यदि रेरा लागू होने के बाद कोई ब्याज दर आवंटी के डिफॉल्ट से प्रोमोटर द्वारा लिया जाता है, तो उसी दर से ब्याज प्रोमोटर द्वारा डिफॉल्ट किये जाने पर भी आवंटी को दिया जायेगा। अतः विलम्बित भुगतान पर शिकायतकर्ता द्वारा भी MCLR+H प्रतिशत की ब्याज दर से ब्याज देय होगा। यदि इससे अधिक दर से कोई धनराशि रेरा लागू होने के बाद आवंटी से विलम्ब हेतु ली गयी है, तो विलम्बित अवधि हेतु ब्याज की धनराशि की भी उसी दर से गणना की जायेगी। इस आदेश की एक-एक प्रति सम्बन्धित पत्रावलियों पर रखी जाये एवं इस आदेश में प्रतिपादित सिद्धान्त के अनुरूप धनराशि व ब्याज की प्रत्येक मामले में गणना की जायेगी। इस आदेश का उल्लघंन भू-सम्पदा (विनियमन तथा विकास) अधिनियम, 20:6 की धारा-63 तथा अन्य सुसंगत प्राविधानों के अन्तर्गत दंडनीय होगा। आदेश पोर्टल पर अपलोड किया जाये। यदि विपक्षी द्वारा इस आदेश का अनुपालन नहीं किया जाता है, तो शिकायतकर्तागण को यह अधिकार होगा कि रेरा प्राधिकरण के माध्यम से अपने आदेश का कियान्वयन करा सकेगें। दिनांक 0 #टव 72०2 ) a / za al (राजीव कुमार) (अध्यक्ष, उ0प्र0 भू-सम्पदा विनियामक प्राधिकरण