Uttar Pradesh Real Estate Regulatory Authority

Anjali Gupta - Pardeep Kumar Gupta v. Cloud 9 Projects Private Limited

Complaint No. NCR144/03/106895/2023

Decision date
2025-09-26
Text availability
Machine-read (OCR) text, unverified
Bench
Adjudicating Officer Gautam Budh Nagar

Source: UP RERA order

Connected provisions and cases

No further provision or case links are recorded.

Judgment text

उ.प्र. भू-सम्पदा विनियामक प्राधिकरण, क्षेत्रीय कार्यालय, गौतमबुद्धनगर पीठ-3 भू-सम्पदा (विनियमन और विकास) अधिनियम 2046 की धारा-34 के अन्तर्गत पारित आदेश उपस्थितः- डा०दीपक स्वरूप सक्सेना, सदस्य क्रम शिकायत संख्या |. | यूनिट | पत्रावली पर उपलब्ध | अपार्टमें अनुबंधानुसार | वांछित ष ao न0 रसीद के अनुसार बायर कब्जा दिये जमा धनराशि रु0 एग्रीमेंट की | जाने की तिथि तिथि I, | ॥८९।44/03/06895/2023 | अंजलि गुप्ता व | 003 | Go 2,49,02,0:7/ | 26.02.2074 | 2। माह यूनिट का प्रदीप कमार अर्थात नवम्बर | कब्जा व गुप्ता ia 2045 विलम्बित अवधि का ब्याज दिलाये जाने का अनुरोध किया गया है। बनाम क्लाउड-9 प्रोजेक्टस प्रा.लि. शिकायतकर्तागण द्वारा विपक्षी के विरूद्ध यूनिट का कब्जा व विलम्बित अवधि का ब्याज दिलाये जाने हेतु यह शिकायत संस्थित की गयी है। संक्षेप में शिकायतकर्तागण का कथन है कि विपक्षी द्वारा संचालित परियोजना LOTUS BOULEVARD ESPACIA (TOWER 37-38, CLUB AND COM) में यूनिट संख्या 4003 बुक कराई गई। आवंटित यूनिट की कूल कीमत vo 4,5,749i2/e जिसके सापेक्ष शिकायतकर्तागण द्वारा विपक्षी को धनराशि wo ,49,02,0i7 /er भुगतान किया गया। शिकायतकर्तागण द्वारा शिकायत पृष्ठ पर यह उल्लिखित किया गया है कि विपक्षी द्वारा टॉवर-37 का निर्माण कार्य पूर्ण नहीं किया गया है। विपक्षी द्वारा बिना सूचना के यूनिट का क्षेत्रफल 2255 sat से बढ़ाकर 2435 soft कर दिया गया है। शिकायतकर्तागण द्वारा विपक्षी को यूनिट के सापेक्ष ore के अनुसार धनराशि का भुगतान किया जा चुका है। अतः शिकायतकर्तागण ने यूनिट का कब्जा व विलम्बित अवधि का ब्याज दिलाये जाने का अनुरोध किया है।

शिकायतकर्तागण द्वारा शिकायत के समर्थन में अपार्टमेंट बायर एग्रीमेंट व रसीदों की छायाप्रतियाँ दाखिल की गयी हैं। शिकायतकर्तागण द्वारा विपक्षी को भुगतान की गई धनराशि का विवरण निम्नवत्‌ है:- a क्रम विवरण दिनांक भुगतान की गई धनराशि संख्या (रु0) गा विपक्षी द्वारा जारी- रसीद संख्या 007922 02.04.2044 BO 3,00,000/ रसीद संख्या 007924 02.04.2044 रु0 50,00,000 / रसीद संख्या 007920 02.04.2044 BO 52,92,9/ रसीद संख्या 007876 02.02.2044 रु0 44,29,06 / रसीद संख्या 007923 02.04.2044 रु0 28,80,000 / | कुल योग : SO ,49,02,07 / पीठ द्वारा विपक्षी को उपस्थिति हेतु व लिखित जवाब दाखिल किये जाने हेतु पंजीकृत डाक व सार्वजानिक नोटिस के माध्यम से सूचित किया गया। इसके उपरांत भी विपक्षी नियत तिथि पर न तो उपस्थित हुए और न ही लिखित जवाब दाखिल किया गया। इस प्रकार विपक्षी पर तामील पर्याप्त मानते हुए पीठ द्वारा दिनांक 05.05.2025 को पत्रावली विपक्षी के विरूद्ध एकपक्षीय कार्यवाही हेतु अग्रसारित करते हुए शिकायतकर्ता की एकपक्षीय बहस सुनी गयी। उपरोक्त वर्णित तथ्यों के कारण प्रकरण में एकपक्षीय निर्णय पारित किया जा रहा है। शिकायतकर्तागण की एकपक्षीय बहस पत्रावली पर उपलब्ध प्रपत्रों पर सुनी गयी। उपलब्ध प्रपत्रों के आधार पर निम्न प्रश्न विरचित किये गये :- 4. क्या रेरा आने से पूर्व के अनुबन्ध रेरा के दायरे में नहीं आते हैं ? तथा क्‍या पक्षकारों के मध्य रेरा लागू होने से पूर्व अनुबन्ध निष्पादित किये जाने पर रेरा के प्राविधान लागू नहीं होगें ? 2. क्‍या शिकायतकर्तागण को कब्जा एवं विलम्बित अवधि का ब्याज दिलाया जाये? यदि हाँ तो ब्याज की क्‍या दर होगी ?

निस्तारण प्रश्न संख्या-4 +- प्रश्न संख्या-4 इस तथ्य पर विरचित है कि क्‍या रेरा आने से पूर्व के अनुबन्ध रेरा के दायरे में नहीं आते है तथा क्‍या पक्षकारों के मध्य रेरा लागू होने से पूर्व अनुबन्ध निष्पादित किये जाने पर रेरा के प्राविधान लागू नहीं होगें ? इस सम्बन्ध में माननीय सर्वोच्च न्यायालय द्वारा सिविल अपील संख्या-6745-6749 / 2024 “मैसर्स न्यूटेक प्रोमोटर्स एंड डेवलपर्स wo feo बनाम उ0प्र0 राज्य व अन्य” में दिया गया आब्जर्वेशन महत्वपूर्ण है, जिसमें स्पष्ट रूप से उल्लिखित किया गया है कि :- "54. From the scheme of the Act 20I6, its application is retroactive in character and it can safely be observed that the projects already completed or to which the completion certificate has been granted are not under its fold and therefore, vested or accrued rights, if any, in no manner are affected. At the same time, it will apply after getting the on-going projects and 2 future projects registered under Section 3 to prospectively follow the mandate of the Act 206." उपरोक्त विधि व्यवस्था से यह स्पष्ट है कि रेरा अधिनियम लागू होने से पूर्व

जो भी अनुबन्ध हस्ताक्षरित हुए या अधिनियम लागू होने से पूर्व की परियोजनाओं, जहाँ पर पूर्णता प्रमाण पत्र सम्प्रवर्तक द्वारा प्राप्त नहीं किया गया है, वहाँ पर अधिनियम का प्रवर्तन पूर्वव्यापी प्रभाव रहेगा। यह भी रेरा अधिनियम में स्पष्ट है कि “ऑन गोईंग” परियोजनायें निश्चित रूप से रेरा अधिनियम की परिधि में आते हैं। उपरोक्त माननीय उच्च न्यायालय के आर्ब्जेवेशन से यह भी स्पष्ट है कि यद्यपि रेरा पंजीकरण से पूर्व प्रोमोटर एवं आवंटी के मध्य अनुबन्ध निष्पादित हुए हैं, परन्तु यदि परियोजना को रेरा में पंजीकरण कराया जाता है, तो रेरा के सभी प्राविधान लागू होगें। विपक्षी द्वारा प्रश्गगत परियोजना को रेरा में पंजीकृत कराया गया है, जिसका पंजीकरण संख्या- UPRERAPRI9290 है। अतः वर्णित तथ्यों के आधार पर यह स्पष्ट है कि विपक्षी की परियोजना वर्तमान में “ऑनगोइईंग प्रोजेक्ट” की श्रेणी में आती है। ऐसी दशा में रेरा के सभी प्राविधान लागू होगें। तद्नुसार प्रश्न eH निस्तारित किया जाता है। निस्तारण प्रश्न संख्या 2 -: प्रश्न संख्या-2 इस आशय का विरचित किया गया है कि क्‍या शिकायतकर्तागण को कब्जा एवं विलम्बित अवधि का ब्याज दिलाया जाये? यदि हाँ तो ब्याज की क्‍या दर होगी? शिकायतकर्तागण का कहना है कि विपक्षी द्वारा संचालित परियोजना में यूनिट बुक करायी गयी थी। विपक्षी द्वारा टॉवर में पूर्ण निर्माण नहीं किया गया है। अत: शिकायतकर्तागण ने यूनिट का कब्जा व विलम्बित अवधि का ब्याज दिलाये जाने का अनुरोध किया है। विपक्षी द्वारा लिखित जवाब व ओ.सी /सी.सी प्राप्त होने का साक्ष्य दाखिल नहीं किया गया है जिससे यह स्पष्ट नहीं है कि विपक्षी की परियोजना पूर्ण है 3 अं

अथवा नहीं और न ही शिकायतकर्तागण द्वारा भी परियोजना पूर्ण होने के सम्बन्ध में कोई साक्ष्य दाखिल किया गया है। पत्रावली पर उपलब्ध प्रपत्रों के अवलोकन से विदित है कि शिकायतकर्तागण व विपक्षी के मध्य दिनांक 26.02.204 को अपार्टमेंट बायर एग्रीमेंट निष्पादित हुआ जिसके अनुसार विपक्षी द्वारा शिकायतकर्तागण को यूनिट का कब्जा 2 माह अर्थात नवम्बर 2045 में दिया जाना था जो अभी तक शिकायतकर्तागण को प्राप्त नहीं हुआ है। उपरोक्त से स्पष्ट है कि विपक्षी की परियोजना लगभग 40 वर्ष से विलम्बित है। चूंकि शिकायतकर्तागण द्वारा यूनिट का कब्जा एवं विलम्बित अवधि का ब्याज दिलाये जाने का अनुरोध किया गया है जिस कारण शिकायतकर्तागण यूनिट का कब्जा व विलम्बित अवधि का ब्याज पाने के अधिकारी है। यहां यह भी उल्लेखनीय है कि शिकायतकर्ता द्वारा शिकायत पृष्ठ पर उल्लिखित किया गया है कि विपक्षी द्वारा यूनिट का क्षेत्रफल 2255 Saft से बढ़ाकर 2435 54६ कर दिया गया है परन्तु शिकायतकर्ता द्वारा बढ़े हुए एरिया का कोई साक्ष्य प्रस्तुत नहीं किया गया है और न ही विपक्षी के द्वारा ऐसा कोई कथन किया गया है जिस कारण serena अनुबंध पत्र में अंकित यूनिट का क्षेत्रफल माना जाएगा। अतः ऐसी स्थिति में साक्ष्य के अभाव में बढे हुए एरिया या घटे हुए एरिया पर कोई आदेश पारित किया जाना समीचीन नहीं होगा। फोर्स मैज्योर के अधीन कब्जा उपलब्ध कराये जाने में हुए विलम्ब के सम्बन्ध में एस ओ पी दिनांकित 08.08.2024 के प्रस्तर 5.4 में यह प्राविधानित किया गया है कि :-

» प्रमोटर द्वारा बायर बिल्डर एग्रीमेंट में कब्जा देने की आश्वासित तिथि (Promised Date) से (फोर्स मैज्योर, माननीय एन.जी.टी, माननीय उच्च न्यायालय अथवा माननीय उच्चतम न्यायालय द्वारा पारित आदेश के कारण बाधित अवधि को घटाते हुए) पूर्णता प्रमाण पत्र अथवा अधिभोग प्रमाण पत्र प्राप्त होने अथवा ऑफर ऑफ पजेशन की तिथि (जो भी बाद में हो ) को विलम्ब की अवधि माना TAT I” माननीय सर्वोच्च न्यायालय द्वारा सिविल अपील संख्या: 73029 / 985, “MLC. Mehta Versus Union of India” में पारित आदेश, दिनांक 04-4-20:9 4 निम्नलिखित निर्देश दिये हैः- “With respect to demolition and construction activities we direct that no demolition and construction activities take place in Delhi and NCR region. In case it is found that such activity is done, the local administration as well as the municipal authorities including the Zonal Commissioners, Deputy Zonal Commissioners shall be personally held responsible for all such activities. They have to act in furtherance of the Court’s order and to ensure that no such activity takes place.” इसके अतिरिक्त उपर्युक्त सिविल अपील संख्या: 73029/4985 में पारित आदेश दिनांक o9-2-20:9 में निम्नलिखित निर्देश दिये है:- “in the affidavit dated 05.2.209, the Central Pollution Control Board (CPCB) has stated as under:-

"2, That it is respectfully submitted that it is normally experienced that in month of December depending upon Climatic Condition the AQI category varies. As a matter of fact, last year (208) 8 days in the month of December were in severe AQI category. Presently the situation not being severe, CPCB is of considered opinion that partial ban could be in place of construction activities in as much as no construction should be permitted during night time (6.00 pm to 6.00 am). The ban imposed could be partially lifted by permitting activities during day time (6.00 am to 6.00 pm), subject to the criteria stipulated in GRAP, wherein strict emforcement of rules for dust control in construction activities and closure of non-compliant sites is mandated in moderate to poor AQI category and further a bank on construction activities may be imposed by EPCA if Ambient AIR quality levels persist in severet+/emergency category for 48 hours or more. "” Hence, the ban is relaxed in terms of the recommendations made by Central Pollution Control Board (CPCB), as quoted above. However, conditions for raising construction be scrupulously followed.” माननीय सर्वोच्च न्यायालय द्वारा (दिनांक o4-i:-209 से दिनांक

44--02-2020 तक) की अवधि के लिए निर्माण कार्य पर रोक लगायी गयी है, जिसमें माननीय सर्वोच्च न्यायालय द्वारा पारित आदेश,दिनांक 09-42-2049 में पूर्ण प्रतिबन्ध को हटाते हुए, आंशिक प्रतिबन्ध लगाया गया। ऐसे में माननीय सर्वोच्च न्यायालय द्वारा 35 दिन (दिनांक 04-44-2049 से दिनांक 09-42-2049) एवं 33 दिन(66+2) (दिनांक 40-42-2049 से दिनांक 44-02-2020 तक Ua 06 बजे से सुबह 06 बजे तक) की अवधि के लिए निर्माण कार्य पर प्रतिबन्ध लगाया गया। इन तथ्यों के आलोक में यह स्पष्ट है कि उक्त अवधि विपक्षी के नियन्त्रण से बाहर थी तथा इसके लिए विपक्षी को उत्तरदायी ठहराना न्‍्यायोचित नहीं होगा। अतः यह निष्कर्ष निकालना उचित होगा कि उपर्युक्त वर्णित दोनो अवधियों के लिए —— SS. 5 परियोजना को पूर्ण होने में हुए विलम्ब के लिए विपक्षी जिम्मेदार नहीं है और इस अवधि में कुल-35 feat 33 दिन अर्थात्‌ 68 दिन निर्माण कार्य WANs रहा है दिन निर्माण कार्य प्रभावित रहने के कारण, विपक्षी इसका लाभ पाने का अधिकारी ह। पाने का अधिकारी है। इसके अतिरिक्त कोविड-49 महामारी के सम्बंध में उ0प्र0 रेरा अथॉरिटी द्वारा दिनांक 06.06.2020 को कोविड-49 (Corona Virus Disease) के प्रभाव के कारण सभी परियोजनाओं को पूर्ण करने हेतु दिनाक 25.03.2020 से 6 माह की अतिरिक्त अवधि अर्थात्‌ दिनांक 25.09.2020 तक की अवधि दे दी गयी है और यह अतिरिक्त अवधि फोर्स मैज्योर इवेन्टस्‌ के कारण मानी जायेगी। इसको दृष्टिगत रखते हुए दिनांक 25.03.2020 से दिनांक 25.09.2020 तक परियोजना में हुए विलम्ब हेतु कोई ब्याज प्रोमोटर द्वारा आवंटियों को नहीं दिया जाएगा और न ही शिकायतकर्ता से कोई विलम्ब ब्याज लिया जायेगा।

उपरोक्त तथ्यों व माननीय उच्चतम न्यायालय के आदेश को दृष्टिगत रखते हुये 68 दिन के अतिरिक्त विपक्षी कोविड-49 के कारण फोर्स मैज्योर का लाभ पाने का अधिकारी है। जहाँ तक किस अवधि तक का ब्याज दिलाये जाने का प्रश्न है। इस सम्बन्ध में सिविल अपील सं0 6649-50 /20:8 "'सुपरटेक लिमिटेड बनाम रजनी गोयल"'में माननीय उच्चतम न्यायालय द्वारा अभिनिर्धारित किया गया है किः- "the period of Interest should close on April 20l6 when the Full Occupancy Certificate was obtained as per the admission of the Respondent — Purchaser herself in Para 4(j) of the Consumer Complaint, wherein she has admitted that the Appellant —Builder had obtained the Completion Certificate as late as April 20l6. The Respondent — Purchaser could not have any further grievance after April 20I6 with respect to delay in handing over possession. The Respondent — Purchaser ought not to be allowed to reap the benefits of her own delay in taking possession. " उपरोक्त विधि व्यवस्था के अनुसार ओ.सी./सी.सी. अथवा कब्जा ऑफर किये जाने की तिथि, जो भी बाद में हो तक शिकायतकर्तागण विलम्ब ब्याज पाने के अधिकारी होगे। जहाँ तक ब्याज देयता का प्रश्न है, माननीय बॉम्बे उच्च न्यायालय द्वारा “नीलकमल रियलटर्स सबअर्बन प्रालि. आदि बनाम यूनियन ऑफ इंडिया“के वाद में अभिनिर्धारित किया गया है कि :-

"Section 8(l)(b) lays down that if the promoter fails to complete or is unable to give possession of an aprtment due to discontinuance of his business as a developer on account of suspension or revocation of the registration under the Act or for any other reason, he is liable on demand to the allottees, in case the allottee wishes to withdraw from the project, without prejudice in this behalf including compensation. If the allottee does not intent to withdraw from the project he shall be paid by the promoter interest for every month's delay till handing over of the possession,. The requirement to pay interest is not a penalty as the payment of interest is compensatory in nature in the light of the delay suffered by the allottee who has paid for his apartment but has not received possession of it. The obligation imposed on the promoter to pay interest till such time as the apartment is handed over to him is not unreasonable, " अतः उपरोक्त निर्णय के आलोक में यह स्पष्ट है कि उ.प्र. Ww के प्राविधानों के अन्तर्गत प्रमोटर व केता के बीच किये गये अनुबंध के अनुरूप विलम्ब तथा मूल धनराशि पर ब्याज देय होगा, क्योंकि प्रमोटर्स द्वारा उक्त धनराशि का उपभोग किया गया है।

जहाँ तक देय ब्याज दर का प्रश्न है, तो राज्य सरकार द्वारा भू-सम्पदा (विनियमन एवं विकास) अधिनियम 20i6 के अधीन दिनांक ॥7.40.2048 को भू-सम्पदा (विनियमन और विकास) (विकय,पटटा के लिए करार) नियमावली 20i8 अधिसूचित की गयी हैं। इसमें संलग्नक के रूप में दिये गये विकय,पटटा विलेख के प्रारूप के प्रस्तर 9 में प्रमोटर्स के डिफाल्ट प्रकरण (Events of default) परिभाषित है, जिसमें प्रस्तर o2(ii) F प्रमोटर के डिफाल्टर होने की स्थिति में आवंटी हेतु प्राविधानित है कि:- "The Allottee shall have the option of terminating the Agreement in which case the Promoter shall be liable to refund the entire money paid by the Allottee under any head whatsoever towards the purchase of the apartment, along with interest at the rate equal to MCLR (Marginal Cost of Lending Rate) on home loan of State Bank of India +% unless provided otherwise under the Rules. within forty-five days of receiving the termination notice 7 _—Ss यही दर आवंटियों के द्वारा डिफॉल्ट की स्थिति में भी प्रस्तर 9.30) में निर्धारित है। उक्त प्राविधान को दृष्टिगत रखते हुए आवंटी को MCLR+9 feet की ब्याज दर पर विलम्बित अवधि का ब्याज दिलाया जाना न्यायोचित प्रतीत होता है। यह भी स्पष्ट किया जाता है कि यदि शिकायतकर्ता की कोई धनराशि अतिदेय है, तो उस पर विपक्षी भी MCLR+I प्रतिशत की दर से ही ब्याज प्राप्त कर सकता है। रेरा की धारा-2(2४)0)में भी यही ब्याज की परिभाषा दी गयी है। उपरोक्त तथ्यों एवं नजीरों के आधार पर शिकायतकर्तागण यूनिट का कब्जा एवं विलम्बित अवधि का ब्याज पाने के अधिकारी है। तदनुसार प्रश्न संख्या-2 निस्तारित किया जाता है।

उपरोक्त प्रश्नों का निस्तारण करते हुए निम्न आदेश पारित किया जाता है। आदेश विपक्षी को आदेशित किया जाता है कि वह आदेश पोर्टल पर अपलोड होने की तिथि से 45 दिन के भीतर शिकायतकर्तागण से अवशेष धनराशि प्राप्त कर, शिकायतकर्ता की यूनिट आवंटन पत्र / अनुबंध के अनुसार समस्त सुविधाओं को पूर्ण कराकर ओसी /सी.सी सहित कब्जा देना सुनिश्चित करें और देय स्टाम्प शुल्क प्राप्त कर नियमानुसार रजिस्ट्री कराएं। विपक्षी द्वारा शिकायतकर्तागण को दिनांक 0.2.205 से दिनांक 30.04.207 तक अनुबंधानुसार विलम्ब ब्याज का भुगतान किया जाएगा। तत्पश्चात दिनांक 04.05.2047 से ओ.सी /सी.सी अथवा कब्जा ऑफर किये जाने की तिथि जो भी बाद में हो तक शिकायतकर्तागण द्वारा जमा धनराशि रु0 4,49,02,047,// पर MCLR+] प्रतिशत ब्याज अदा करना सुनिश्चित करें। ब्याज की यह धनराशि अंतिम भुगतान की जाने वाली धनराशि में समायोजित की जायेगी। ब्याज की धनराशि देय धनराशि से अधिक होने पर नियमानुसार शिकायतकर्तागण को वापस की जायेगी। निस्तारण प्रश्न संख्या 2 के अनुसार फोर्स मैज्योर पीरियड को दृष्टिगत रखते हुए (माननीय उच्चतम न्यायालय द्वारा सिविल अपील संख्या 43029 / 985 के अनुसार ) 68 दिन तथा दिनांक 25.03.2020 से दिनांक 25.09.2020 तक परियोजना में हुए विलम्ब हेतु मा... 8 ब्याज की गणना नहीं की जायेगी। साथ ही यदि शिकायतकर्तागण का कोई अतिदेय (Over Dues) है, तो उस पर भी इस अवधि का ब्याज देय न होगा।

विपक्षी को यह निर्देशित किया जाता है कि रेरा अधिनियम, 2046 की धारा Aza)(i) के अनुसार यदि रेरा लागू होने के बाद कोई ब्याज दर आवंटी के डिफॉल्ट से प्रोमोटर द्वारा लिया जाता है, तो उसी दर से ब्याज प्रोमोटर द्वारा डिफॉल्ट किये जाने पर भी आवंटी को दिया जायेगा। अतः विलम्बित भुगतान पर शिकायतकर्तागण द्वारा भी ॥४0,२++ प्रतिशत की ब्याज दर से ब्याज देय होगा। यदि इससे अधिक दर से कोई धनराशि रेरा लागू होने के बाद आवंटी से विलम्ब हेतु ली गयी है, तो विलम्बित अवधि हेतु ब्याज की धनराशि की भी उसी दर से गणना की जायेगी। इस आदेश का veers भू-सम्पदा (विनियमन और विकास) अधिनियम, 2046 की धारा-63 तथा अन्य सुसंगत प्राविधानों के अन्तर्गत दंडनीय होगा। विपक्षी द्वारा यदि इस आदेश का अनुपालन 45 दिन में नहीं किया जाता है, तो शिकायतकर्ता रेरा प्राधिकरण के माध्यम से आदेश का कियान्वयन करा सकेगें। आदेश पोर्टल पर अपलोड किया जाये। es Pe पका (डा०दीपक स्वरूप सक्सेना) सदस्य उ.प्र. भू-सम्पदा विनियामक प्राधिकरण गौतमबुद्धनगर