Uttar Pradesh Real Estate Regulatory Authority
Surendra Kumar Khare v. Project Category-Un-Register Imperia Structures Ltd
Complaint No. NCR144/02/105947/2023
- Decision date
- Not recorded
- Text availability
- Machine-read (OCR) text, unverified
- Bench
- Bench 2
Source: UP RERA order
Connected provisions and cases
No further provision or case links are recorded.
Judgment text
English translation. Machine translation from the Hindi by AI (Gemini 3.8 Flash, Antigravity), not reviewed. The original order below is the authoritative text.
E-Court U.P. Real Estate Regulatory Authority State Planning Institute, New Building, Kalakankar House, Old Hyderabad, Lucknow--226007 Hearing Bench - Unregistered Project Presiding Officer - Shri Harish Tripathi, Adjudicating Officer
| S.No. | Complaint Number | Complainant | Referred Order | Project (MOU) | Project (Other Documents) | | 1 | NCRI44/02/I05833/2023 | Mohd. Ateeq [मो. atef] | 09.05.2023 | 28-05-20I5 | H2O IT & H2O IT PARK (TRIPARTITE SUB-LEASE DEED) | | 2 | स्टारा44/02/05949/2023 | Ruchi Srivastava | 09.05.2023 | 2-05-20I5 | IMPERIA MO0IT ONYX SPACE | | 3 | ८२44/03/06303/2023 | Ravindra Narula and Geeta Sharma | 09.05.2023 | 09-02-205 | IMPERIA H20 IT ONYX SPACE | | 4 | NCRI44/03/I0662/2023 | Umesh Varshney and Piyush Nandan | 09.05.2023 | 2I-I0-203 | IMPERIA H20 IT ONYX SPACE & H20 IT PARK (TRIPARTITE SUB-LEASE DEED) | | 5 | NCRI44/02/06077/2023 | Kanwalsunir Singh Sarang | 09.05.2023 | :9-07-20i5 | HO IT | | 6 | NCRI44/02/0583/2023 | Nilofer | 09.05.2023 | «4-03-.20i5 | H20 IT PARK | | 7 | फ्टारा44/03/06236/2023 | Sabita Gupta and Samrat Gupta | 09.052023 | ॥-02-20i5 | IMPERIA H20 IT ONYX SPACE & 20 IT PARK (TRIPARTITE SUB-LEASE DEED) | | 8 | पटारा44/02/0633/2023 | Mashkoor Alam | 09.05.2023. | 03.02.20I4 | H20 IT ONYX SPACE | | 44 | बिटार44/02/05856/2 023 | Khurram Shamsi | 09.05.2023 | 0I-06-205 | IMPERIA H20 IT ONYX SPACE & H20 IT PARK (TRIPARTITE SUB-LEASE DEED) | | 32 | तारा44/02/05862/2023 | Prashant Kumar Jha and Kanchan Kumari | 09.05.2023 | 26-04-204 | IMPERIA H20 IT ONYX SPACE & H20 IT PARK (TRIPARTITE SUB-LEASE DEED) | | 43 | ८२44/02/05926/2023 | Surendra Kumar Khare | 09.05.2023 | 0-i2-205 | IMPERIA H20 IT ONYX SPACE | | 44 | ४(८.२।44/02/05947/2023 | Prashant Kumar Jha and Kanchan Kumari | 09.05.2023 | 4.0.20I4 | IMPERIA ONYX aes | | 35 | पटारा44/02/05943/2023 | Shruti Mishra and Mukesh Mishra | 09.05.2023 | 0.I2.20I5 | IMPERIA ONYX H20 IT SPACE | | i6 | घ९(7२44/02/05865/2023 | | | | | | 9 | पटार44/02/0609/2023 | Ramneek Arora | 09.05.2023 | I]-0-206 | ONYX H20 IT SPACE | | 40 | पटारा44/02/05855/2023 | Gurmeet Kaur and Asha Singh | 09.05.2023 | 72-04-206 | ONYX |
Versus Imperia Structures Ltd. Section-3 / 59 RERA Act Facts The complaints mentioned in the table are against the same promoter and the same project. Therefore, to avoid repetition and for the sake of convenience, they are being disposed of together. During the hearing of the complaints before the present Hon'ble Bench-2 NCR (formerly Hon'ble Bench-4 NCR), a question arose regarding the registration of the respondent's project in RERA. Therefore, the Hon'ble Bench, vide its order dated 09.05.2023, referred the record to this Bench to decide whether the said project is registered / eligible for registration in RERA or not. In the hearing on 09.05.2023, it was admitted by the respondent before the Hon'ble Bench that the said project is not registered in RERA. This statement of the respondent has been recorded in the order sheet. Hearing was conducted through video conferencing. On the date of arguments, the complainants were not present. On behalf of the respondent, learned counsel Shri Vaibhav Sahi was present, whose arguments were heard. Complainants' Arguments / Version
In the written arguments dated 09.05.2024, uploaded on the portal on 0.05.2024, it has been averred by the complainants that the respondent's project ONYX IT TOWER IMPERIA H20 OFFICE SUITES, GREATER NOIDA WEST GAUTAM BUDDH NAGAR is being developed on Plot Nos. -44 and 45 of Knowledge Park-5, which has not been registered in RERA. In complaint number ncri44/09/62I69/2020 Abhiyank Sinha versus Imperia Structures Ltd., the Hon'ble Bench-4, NCR, vide its order dated 45.07.2022, finding the project eligible for registration, directed the respondent to get the project registered in RERA within 03 months; despite this, registration has not been done.
No Builder Buyer Agreement has been executed by M/s Times Shopee Centre P.Ltd. In the partial completion certificate, the project IMPERIA H20 OFFICE SUITES is not mentioned. In this partial completion certificate, no project name is specifically recorded. The MOU in respect of units was entered into with the complainants by M/s Imperia Structures Ltd. The application to the Development Authority for sanction of layout plan was submitted by M/s Times Shopee Centre P.Ltd. in the year 204. There is no mention of M/s Times Shopee Centre Pvt. Ltd. in the MOU. IMPERIA H20 IT SPACE ONYX TOWER is registrable under Section-3 of the RERA Act. The respondent, misleading the RERA Authority on the basis of a partial occupancy certificate, is making a claim that the project is not registrable. The respondent has till date not obtained any completion / occupancy certificate for the project IMPERIA H20 IT SPACE ONYX TOWER. Partial OC has been issued in favor of M/s Times Shopee Centre P.Ltd. M/s Imperia Structures Ltd. and M/s Times Shopee Centre P.Ltd. are both separate companies, whose CIN numbers are different. In support of their version, the complainant has filed a copy of the order dated 45.07.2022 passed by the Hon'ble Bench in the aforesaid complaint, letters of the Development Authority dated 06.03.2047, 23.08.2044, 7.07.20i8, 04.08.2020, 07.09.2020, 14.05.2048, 07.08.2020, 27.07.20:8, and information obtained under Right to Information dated 04.09.2049.
Respondent's Version / Arguments Written statement dated 04.04.2024 and written arguments dated 06.06.2024 were submitted on behalf of the respondent, which were uploaded on the portal on 30.07.2024, and being extremely faint, are not clearly legible. The respondent states that the project is "Imperia H2O IT Space". M/s Times Shopee Centre P.Ltd. is the owner of the land on which the project is being developed. The respondent is only the developer. The occupancy certificate has been issued in favor of the land owner. Development work in the project is being carried out in a phased manner.
According to the Explanation to Section-2 of the RERA Act, a project can be developed and registered in RERA in a phased manner. Due to construction in a phased manner, construction work of some buildings has been completed, while construction work of some buildings is pending. Therefore, the respondent submitted an application for completion certificate for a separate building. According to the respondent, under the provisions of Section-3(2)(b) of the RERA Act, if completion certificate has been received prior to the commencement of the Act, registration of such project in RERA is not required. The completion certificate and occupancy certificate of the project "Imperia H2O IT Space" have already been issued on 06.03.2047. According to paragraph-8 of the respondent's written statement, the project "Imperia H2O IT Space" comes under UMBRELLA PROJECTS IMPERIA H20, whose completion certificate had already been issued prior to the commencement of the Act. The respondent also states that in complaint number 481144/03/724723/2024 Sukhmal Chand Jain versus Imperia Structures Pvt. Ltd. and ॥482144/04/88742/2022 Pankaj Kumar versus Imperia Structures Pvt. Ltd., the Hon'ble Bench of the RERA Authority has already observed that the project is not registrable under Section-3. The complainants have only filed the MOU and have not filed any receipts related to payment.
In support of its arguments, reliance has been placed on behalf of the respondent on the judgment of the Hon'ble Supreme Court in M/s Newtech Promoters and Developers Ltd. versus State of U.P., Civil Appeal No. 6745-6749 / 2024, and the judgment of the Hon'ble Punjab and Haryana High Court in Experion Developers Pvt. Ltd. versus State of Haryana, CWP/7852/2022. Legal Position
First, it is pertinent to examine the legal position in this regard. Section-3 of the RERA Act provides for registration of real estate projects. According to the provisions of Section-3, such project which fell in the category of an Ongoing project on the date of commencement of the Act is registered / eligible for registration in RERA. According to the provisions of Section 3(1) of the Act, no promoter shall advertise, market, book, sell or make agreement for sale in any manner for any building, apartment or plot in a planning area. The provisions of Section-3(1) are as follows: Section 3-Prior registration of real estate project with Real Estate Regulatory Authority. (1) No promoter shall advertise, market, book, sell or offer for sale, or invite persons to purchase in any manner any plot, apartment or building, as the case may be, in any real estate project or part of it, in any planning area, without registering the real estate project with the Real Estate Regulatory Authority established under this Act: Provided that projects that are ongoing on the date of commencement of this Act and for which the completion certificate has not been issued, the promoter shall make an application to the Authority for registration of the said project within a period of three months from the date of commencement of this Act.
From a perusal of the first proviso to Section-3(1) of the RERA Act, it appears that for projects which fell in the category of ongoing projects on the date of commencement of the Act and for which completion certificate had not been issued, registration in RERA was mandatory. The date of commencement of the Act is 04.05.2046, that is, a project whose completion certificate had been issued prior to 01.05.20i6 would not be deemed an ongoing project and its registration would not be mandatory. The Hon'ble U.P. REAT Appellate Tribunal, in Anshul Agarwal versus M/s Uppal Chadha Hi-Tech Developers Pvt. Ltd., Appeal No. 575/2024 decided on 37.05.2023, held in paragraph-7.26 of the judgment that if the completion/occupancy certificate of the project was not issued on the date of coming into force of the Act, i.e., 0.05.206, the project would be deemed an ongoing project and its registration in RERA would be mandatory.
In this judgment, the Hon'ble Appellate Tribunal, after due consideration of the provisions of the Urban Planning and Development Act 4973, U.P. Apartment (Promotion of Construction, Ownership and Maintenance) Act, 2040, RERA Act and Rules, 2046, and after considering the Explanation to Section-4(5) of the Apartment Act, 2040, held that "completion" means the entire construction or the construction of an independent block. Obtaining a completion certificate for the construction of one block of a project is only for the purpose of handing over possession. Notwithstanding the issuance of a completion / occupancy certificate for one block, until the entire construction / development work of the project is completed, the project shall be deemed an ongoing project. An ongoing project is not defined under the RERA Act, 2046.
Rule-2(1)(h) of the RERA Rules, 2046, defining ongoing project, provides which projects require registration in RERA and which projects do not require registration in RERA. Rule-2(1)(h) of the RERA Rules, 2046 is as follows: (h) "ongoing project" means a project where development is going on and for which completion certificate has not been issued but excludes such projects which fulfill any of the following criteria on the date of notification of these rules: (i) where services have been handed over to the Local Authority for maintenance. (ii) where common areas and facilities have been handed over to the Association for the Residents’ Welfare Association for maintenance. (iii) where all development work have been completed and sale/lease deeds of sixty percent of the apartment/houses/plots have been executed. (iv) where all development works have been completed and application has been filed with the competent authority for issue of completion certificate.
According to the provisions of Rule-1(2) of the RERA Rules, 20i6, the Rules shall come into force from the date of publication in the Gazette. Publication of the Rules in the Gazette was made vide NOTIFICATION NO. 438/ViI!-3-26-65 VIVIDH-6, DATED- 27-0-2046, PUBLISHED IN U.P. GAZETTE, EXTRA PART-4, SECTON (ka), DATED- 27-0-206. Thus the date of coming into force of the RERA Rules, 20i6 is 27.40.206. According to the provisions of Rule-2(1)(h) of the RERA Rules, 20i6, a project for which completion certificate was not issued on the date of notification of the Rules, 27.4020I6, shall fall in the category of an Ongoing project and its registration in RERA shall be mandatory. In Rule-2(1)(h)(i), (ii), (iii) & (iv), 04 criteria have been stated. A project fulfilling any of these four criteria, notwithstanding non-issuance of completion certificate, shall be deemed outside the category of an Ongoing project and registration of such project in RERA shall not be mandatory.
Section 59 of the RERA Act provides for penal prosecution and punishment of imprisonment up to 03 years for violation of the provisions of Section-3 by the promoter. If the promoter does not register the project in RERA, there is a provision for imposing a penalty which may be 10 percent of the estimated cost of the project. If the promoter does not deposit the penalty imposed, there is a provision for penal prosecution of the promoter and punishment up to 03 years of imprisonment. The provisions of Section-59 are as follows: Section 59- Punishment for non registration under section 3. (1) If any promoter contravenes the provisions of section 3, he shall be liable to a penalty which may extend up to ten per cent. of the estimated cost of the real estate project as determined by the Authority. (2) If any promoter does not comply with the orders, decisions or directions issued under sub-section (1) or continues to violate the provisions of section 3, he shall be punishable 8222 imprisonment for a term which may extend up to three years or with fine which may extend up to a further ten per cent. of the estimated cost of the real estate project, or with both. Conclusion On the basis of the pleadings of both parties, the evidence adduced, and the arguments advanced in oral submissions, the following point for determination arises: 1. Whether the project is registered / eligible for registration in RERA? Point for Determination-1
The complainants state that the respondent has not registered the project in RERA. Without getting registered, units in the project are being bought and sold. Possession is not being given within the stipulated time. Terms of the agreement for sale are being violated. The respondent has violated the provisions of Section-3 of the RERA Act. Therefore, legal action be taken against it. The respondent states that registration of its project in RERA is not mandatory. On the date of commencement of the Act, the respondent's project did not fall in the category of an Ongoing project, because prior to the commencement of the Act itself, on 06.03.2047, occupancy certificate of the project had been issued by the Development Authority. Now this fact has to be examined whether the respondent's project is exempt from registration in RERA under Section 3(2)(b) read with Rule-2(1)(h) of the RERA Rules. The main ground for exemption from registration stated by the respondent is that the occupancy/completion certificate of the project had already been issued on 06.03.207. On the basis of this occupancy/completion certificate, the Bench of the Hon'ble Authority, in complaint number ॥3(444/03/724723/2024 Sukhmal Chand Jain versus Imperia Structures Pvt. Ltd. and NCRI44/02/8872/2022 Pankaj Kumar versus Imperia Structures Pvt. Ltd., had accepted that the project falls under the exception of Section-3 because occupancy / completion certificate had been obtained by the promoter.
To rebut the aforesaid argument of the respondent, it was stated on behalf of the complainants that no such view has been expressed by the Hon'ble Bench in the aforesaid complaints that the project is not registrable in RERA. On the contrary, in complaint number 8444/09/6469/2020 Abhiyank Sinha versus Imperia Structures Ltd., the Hon'ble Bench-1, NCR, vide its order dated 45.07.2022, finding the project eligible for registration, directed the respondent to get the project registered in RERA within 03 months; despite that, registration has not been done. From a perusal of the record based on the arguments of both parties, it appears that the respondent has not filed copies of the decisions mentioned in its written statement. The complainant has filed a copy of the decision passed in the mentioned complaint in support of its statement.
A perusal of both decisions cited by the respondent on the RERA portal reveals that in the aforesaid complaint of Sukhmal Chand Jain, nothing has been held by the Hon'ble Bench that the project is not registrable in RERA. The Hon'ble Bench, in its decision dated 27.04.2022, merely quoted paragraph-54 of the judgment passed by the Hon'ble Supreme Court in M/s Newtech Promoters and Developers Pvt. Ltd. The respondent, drawing a misleading interpretation of the order of the Hon'ble Bench, in paragraph-10 of its written statement, alleged paragraph-54 of the judgment passed by the Hon'ble Supreme Court in M/s Newtech Promoters and Developers Pvt. Ltd. as being the finding of the Hon'ble Bench. In paragraph-10 of the written statement, the respondent mentioned that the Hon'ble Bench has held that the project is not registrable. In this regard, it is noteworthy that this is not any view of the Hon'ble Bench, but merely a quotation of paragraph-54 of the judgment passed by the Hon'ble Supreme Court.
As far as the second decision ॥84144/04/88742/2022 Pankaj Kumar versus Imperia Structures Pvt. Ltd. is concerned, perusal of the judgment and order dated 02.11.2022 passed in this complaint available on the portal reveals that the Hon'ble Bench expressed no such opinion in its order that the project is not registrable in RERA. The Hon'ble Bench, keeping the complaint in ABEYANCE, passed an order for enquiry and proceedings regarding registration of the project within 03 months. The Hon'ble Bench directed Secretary RERA to ensure whether the project is eligible for registration in RERA or not? Thus, in both the complaints mentioned by the respondent in support of its argument, no such order was passed by the Hon'ble Bench that the project is not registrable in RERA. Thus, the 02 complaints mentioned by the respondent in support of its argument do not support the respondent's argument in any manner.
On the contrary, the complainants, in support of their argument, relied upon the order dated 45.07.2022 passed by the Hon'ble Bench-1, NCR in complaint number NCRI44/09/669/2020 Abhiyank Sinha versus Imperia Structures Ltd. A perusal of the aforesaid order dated 45.07.2022 passed by the Hon'ble Bench-1, NCR reveals that the Hon'ble Bench directed the respondent to get the project registered in RERA within 03 months. Along with this, for non-registration in RERA, Secretary RERA was directed to take lawful action. In this regard, it is appropriate to mention points 2, 3 and 4 of the operative portion of the order dated 45.07.2022. Points 2, 3 and 4 are as follows: "2. The respondent is directed to ensure registration of the project in question in RERA within the upcoming 3 months. 3. Secretary, RERA, shall take lawful action in accordance with the RERA Act for non-registration of the project in RERA by the respondent. 4. A copy of this order be sent to Secretary, RERA for further action."
Thus, from the order of the Hon'ble Bench, it is clear that after applying its judicial mind to the registrability of the project, the Hon'ble Bench found the project eligible for registration in RERA. An order was also given to the respondent to register the project in RERA within 3 months. Directions were also issued to Secretary RERA to take legal action against the respondent for not registering the project in RERA. Despite the aforesaid order of the Hon'ble Bench, the respondent has not registered the project in RERA till date. The respondent states that the completion certificate / occupancy certificate of its project had already been issued on 06.03.2077. For this reason, the project is not registrable in RERA. In this regard, in paragraph-6 of the written statement, special emphasis has been placed on behalf of the respondent on the provisions of Section-3(2)(b) of the RERA Act.
Perusal of the provisions of Section-3(2)(b) reveals that for projects whose completion certificate had been received prior to the date of commencement of the Act, registration in RERA would not be mandatory. According to the provisions of the first proviso to Section-3(1), a project whose completion certificate had not been issued on the date of commencement of the Act shall be deemed an ONGOING project, which had to be mandatorily registered in RERA within 03 months. Under both provisions of Section-3(2)(b) and the first proviso to Section-3(1), the material date for determining an ONGOING project / project registrable in RERA and for issuance of completion certificate is given as the date of commencement of the Act, i.e., 04.05.2046. The Hon'ble U.P. REAT Appellate Tribunal has also held in paragraph-7.26 of the judgment in Anshul Agarwal versus M/s Uppal Chadha Hi-Tech Developers Pvt. Ltd., Appeal No. 575/2024 decided on 37.05.2023, that if the completion / occupancy certificate of the project was not issued on the date of commencement of the Act, i.e., 04.05.206, then the project shall be deemed an ongoing project and its registration in RERA would be mandatory.
Based on the aforesaid argument of the respondent, perusal of the record reflects that no completion certificate has been submitted on behalf of the respondent. The certificate submitted by the respondent is an occupancy certificate. This occupancy certificate is also partial, which has been issued not for the entire block, but in respect of Part IT Block-1 and Part Residency Block-1. This implies that there are several blocks in the project. The partial occupancy certificate is for a part of IT Block-1 and Residency Block-1, meaning that construction work of the other part of IT Block-1 and Residency Block-1 is not complete. If there are 4 blocks in a project and partial occupancy certificate of only one part of one block is issued, then on that basis, the entire project cannot be deemed complete.
Even if for the sake of argument it is assumed that on 06.03.2047 completion certificate / occupancy certificate of the entire project was obtained, even then the project would be deemed an Ongoing project under Section-3, because the date of commencement of the Act is 01.05.20:6, meaning that the partial occupancy certificate is subsequent to the date of commencement of the Act. Therefore, on the basis of this partial occupancy certificate, the respondent's project cannot be considered outside the category of an Ongoing project. The respondent's project shall be deemed an Ongoing project on the date of commencement of the Act 01.05.20:6, and its registration in RERA would be mandatory. For this reason, the Hon'ble Bench, in its aforesaid order dated 15.07.2022, also directed the respondent to get the project registered. Otherwise also, perusal of this partial occupancy certificate dated 06.03.2047 reflects that this partial occupancy certificate has been issued in favor of M/s Times Shopee Centre P.Ltd. No partial occupancy certificate has been issued in favor of the respondent Imperia Structures Ltd.
The respondent states that M/s Times Shopee Centre P.Ltd. is the owner of the land related to the project and the respondent is the developer. When the owner of the land related to the project is someone else and the development of the project is carried out by another person, then in such a case, a collaboration agreement or any other contract or MOU is executed between both parties. When asked in this regard during the hearing, the respondent admitted that no such document has been filed by it, whereas sufficient and reasonable opportunity was given to the respondent to present its case and submit documents.
On this point, it is appropriate to mention paragraph-7.49 of the judgment of the Hon'ble U.P. REAT Appellate Tribunal in Anshul Agarwal versus M/s Uppal Chadha Hi-Tech Developers Pvt. Ltd., Appeal No. 575/2024 decided on 37.05.2023. The Hon'ble U.P. REAT Appellate Tribunal, in paragraph-7.49 of the judgment, after due consideration of the provisions of the Urban Planning and Development Act 4973, U.P. Apartment (Promotion of Construction, Ownership and Maintenance) Act, 2040, RERA Act and Rules, 2046, and after considering the Explanation to Section-4(5) of the Apartment Act, 2040, held that "completion" means the entire construction or the construction of an independent block. Obtaining a completion certificate for the construction of one block of a project is only for the purpose of handing over possession. Notwithstanding the issuance of a completion / occupancy certificate for one block, until the entire construction / development work of the project is completed, the project shall be deemed an ongoing project. In paragraphs-4, 5 and 6 of its written statement, the respondent has stated that phase-wise development of the project is being carried out by it. According to the respondent, under the Explanation to Section-2 of the RERA Act, each phase can be registered separately.
Based on this argument of the respondent, the legal position was considered. Various definitions are given under Section-2. There is no Explanation under this section. In the Explanation to Section-3 of the Act, the position regarding phase-wise development of a project has been clarified, according to which each phase shall be a project in itself. The respondent states that phase-wise development of the project is being carried out by it, but no such record has been submitted by the respondent to show into how many phases the project is being developed, what is being constructed in which phase, construction of how many phases has been completed, construction of how many phases is remaining, and under which phase the units allotted to the complainants fall. Regarding allotment of units, perusal of the MOU of lead complaint no.-1 available on the record reflects that on page-2 of the MOU, the name of the project is recorded as PROJECT OF M/S OFFICE SPACE CALLED ‘ONYX’. In the No Dues Certificate dated 2644. 20i8 issued by the respondent in favor of the complainant, the name of the project is mentioned as "ONYX". On record is a tripartite sub-lease deed which is purported to be executed between Greater Noida Industrial Development Authority, Times Shopee Centre Pvt. Ltd. and the allottee / complainant, wherein the name of the project is mentioned as "H2O IT PARK". Similarly, in other complaints also, different names of the project have been given in different documents.
In its written statement, the respondent has also averred that the complainants, after getting the registry done in their favor, also took possession; despite this, the complaints have been filed. Therefore, the complainants' complaints are the result of an afterthought, in which there is no substance. Exemption from registration in RERA is being claimed by the respondent on the basis of issuance of occupancy certificate of the project. According to the respondent, the project has been completed, whose occupancy certificate has already been issued on 06.03.2047; therefore, registration in RERA is not required and hence registration in RERA has not been done. The complainant has filed letters issued by Greater Noida Industrial Development Authority dated 23.03.2044, 44.07.2048, 27.07.208, 07.08.2020, 07.09.2020, 04.08.2020 and 74.05.20i8, perusal of which reveals that on 23.03.204, the layout plan of the project was approved by the Development Authority on Plot-44-45, SECTOR- KNOWLEDGE PARK-V, GREATER NOIDA. Perusal of various other letters reveals that applications have been submitted by the respondent before the Authority for approval of revised layout plan, which are pending consideration before the Authority. Perusal of letter dated 14.05.20i8 reveals that after considering the application submitted for layout change, the Development Authority, in its letter dated 44.05.208, recorded a total of 15 objections and expected the respondent to remove the objections.
According to public information obtained by the complainants under Right to Information from the Assistant Public Information Officer of Planning Section vide Ref: Niyo./RTI/2049/5829 dated 04.09.2049, an application has been made by Times Shopee Centre Pvt. Ltd. for approval of revised layout plan on Plot No. 44-45, SECTOR- KNOWLEDGE PARK-V, GREATER NOIDA, which layout plans have not been approved till date. From the above discussion and analysis, it is clear that the respondent's project was an Ongoing project on the date of commencement of the Act. Even today, the project is not complete. Revised layout plan is under consideration before the Development Authority. The Hon'ble Bench, in its order dated 45.07.2022, had earlier also directed the respondent to get the project registered in RERA within 03 months; despite this, the registration of the project has not been done by the respondent till date. Therefore, for protection of the interests of home buyers / allottees, registration of the project in RERA is necessary. Order The complaints of the complainants are allowed. The project is an Ongoing project. Therefore, registration of the project in RERA is necessary. The file be forwarded to Secretary, U.P. RERA for further proceedings regarding registration. Dated: 24.08.2024 (Harish Tripathi) Adjudicating Officer
Original order
E-Court उ.प्र. भू-सम्पदा विनियामक प्राधिकरण राज्य नियोजन संस्थान, नवीन भवन, कालाकांकर हाउस, पुराना हैदराबाद, लखनऊ--226007 सुनवाई पीठ-अपंजीकृत परियोजना Torin अधिकारी-श्री हरीश त्रिपाठी, न््यायनिर्णायक् अधिकारी | शिकायत संख्या शिकायतकर्ता | संदर्भित | परियोजना | परियोजना सं. | आदेश (MOU) (Other | = | | Documents) | + | NCRI44/02/I05833/2023 | मो. atef 09.05.2023 28-05- | H2OIT& Sra 20I5 | H2OIT PARK | ONYX — (TRIPARTITE SUB-LEASE | | | | |. DEED) 2 |स्टारा44/02/05949/2023 रूचि 09.05.2023 | 2-05- IMPERIA श्रीवास्तव 20I5 MO0IT | ONYX SPACE = aie | + } | : ८२44/03/06303/2023 रविन्द्र 09.05.2023 | 09-02- IMPERIA नरूला एण्ड | 205 H20 IT |_| | गीता शर्मा | | ONYX | SPACE 4 | NCRI44/03/I0662/2023 Ueda 09.05.2023 | 2I-I0- IMPERIA वार्ष्णय एण्ड 203 H20 IT पियूष नंदन ONYX SPACE & KS H20 IT PARK | (TRIPARTITE | SUB-LEASE | | | | | DEED) 5 | NCRI44/02/06077/2023 | कंवलसुनीर 09.05.2023 | :9-07-, HO IT | सिंह सारंग | te | 6 |NCRI44/02/0583/2023 "fre | 09.05.2023 | «4-03-. | H20IT PARK | | नीलोफर | ae | | ॥ 7 फ्टारा44/03/06236/2023 | सबिता गुप्ता | 09.052023 | ॥-02-.. | IMPERIA | एण्ड सम्राट 20i5 H20 IT : गुप्ता ONYX SPACE& | J | 20 IT PARK | (TRIPARTITE | SUB-LEASE | | | | | DEED) 8 |पटारा44/02/0633/2023 | मशकूर| 09.05.2023. | 03.02.20I4 H20 IT आलम | ae ONYX | SPACE Page I of 4 a 44 | बिटार44/02/05856/2 023 32 |टारा44/02/05862/2023 | 43 | ८२44/02/05926/2023 | 44 | ४(८.२।44/02/05947/2023 35 | पटारा44/02/05943/2023 i6 घ९(7२44/02/05865/2023 9 | पटार44/02/0609/2023 | रामनीक
| 40 | पटारा44/02/05855/2023 | गुरूमीत कौर E-Court =| : 7 | अरोरा ONYX H20 IT en विन | __ SPACE 09.05.2023 I]-0- एण्ड आशा | 206 सिंह ONYX गुरूमीत कौर | 09.05.2023 | 72-04 | हु एण्ड आशा 206 सिंह ONYX खुर्रम शमसी | 09.05.2023 | 0I-06- | IMPERIA 205 H20 IT ONYX SPACE & H20 IT PARK (TRIPARTITE SUB-LEASE | DEED) | प्रशान्त 09.05.2023 | 26-04- IMPERIA 204 H20 IT कमार झा wes कंचन | ONYX SPACE & 8 H20 IT PARK कुमारी (TRIPARTITE SUB-LEASE है | - — DEED) | सुरेन्द्र कुमार | 09.05.2023 | 0-i2- IMPERIA खरे 205 H20 IT ONYX | SPACE __| प्रशान्त 09.05.2023 | 4.0.20I4| IMPERIA कुमार झा ONYX aes एण्ड कंचन | कुमारी हा ह _| | श्रुति मिश्रा | 09.05.2023 | 0.I2.20I5| IMPERIA एण्ड मुकेश ONYX H20 IT मिश्रा SPACE बनाम इम्पीरिया स्ट्रक््चर्स लि. धारा-3 /59 रेरा अधिनियम तथ्य तालिका में वर्णित शिकायतें एक ही प्रमोटर एवं ही परियोजना के विरूद्ध है। अतः पुनरावृत्ति से बचने एवं सुविधा की दृष्टि से इनका निस्तारण एक "GZ जा रहा है। Page 2 एव 76 E-Court वर्तमान मा. पीठ--2 एन.सी.आर. (पूर्व में मा. पीठ-4 एन.सी.आर.) के समक्ष शिकायतों की सुनवाई के दौरान विपक्षी की परियोजना को रेरा में पंजीकरण होने के सम्बंध में प्रश्न उत्पन्न हुआ। अतः मा. पीठ ने अपने आदेश दिनांक 09.05.2023 द्वारा पत्रावली को इस पीठ को यह विनिश्चिय करने के लिए संदर्भित किया गया कि an उक्त परियोजना रेरा में पंजीकृत / पंजीकरण होने योग्य है अथवा नहीं? दिनांक 09.05.2023 की सुनवाई में विपक्षी द्वारा मा. पीठ के समक्ष यह स्वीकार किया गया है कि उक्त परियोजना रेरा में पंजीकृत नहीं है। विपक्षी का यह कथन आदेश पत्र में अंकित किया गया है।
वीडियो कॉन्फ्रेंसिंग के माध्यम से सुनवाई की गयी। बहस की तिथि पर शिकायतकर्ता उपस्थित नहीं हुए। विपक्षी की ओर से विद्वान अधिवक्ता श्री वैभव साही उपस्थित हुए, जिनकी बहस सुनी गयी। शिकायतकर्तागण का तर्क / पक्ष कथन शिकायतकर्तागण द्वारा लिखित बहस दिनांकित 09.05.2024, जो पोर्टल पर दिनांक 0.05.2024 को अपलोड की गयी है, में यह अभिकथन किया गया है कि विपक्षी की परियोजना ONYX IT TOWER IMPERIA ४20 OFFICE SUITES, GREATER NOIDA WEST GAUTAM BUADDH NAGAR में नॉलेज पार्क-5, के प्लाट संख्या -44 एवं 45 पर विकसित की जा रही है, जिसका रेरा में पंजीकरण नहीं कराया गया है। शिकायत संख्या ncri44/09/62I69/2020 अभियांक सिन्हा बनाम इम्पीरिया स्ट्रक््चर लि. में मा. पीठ--4, एन.सी.आर. द्वारा दिनांक 5.07.2022 को परियोजना को पंजीकरण योग्य पाते हुए विपक्षी को आदेशित किया था कि विपक्षी 03 माह के अन्दर परियोजना का रेरा में पंजीकरण कराये। मा. पीठ के आदेश के बावजूद पंजीकरण नहीं कराया गया है।
रेरा नियमावली दिनांक 27..0206 को लागू हुई, तब परियोजना चल रही (Ongoing) परियोजना की श्रेणी में आती थी। विपक्षी द्वारा जो आंशिक अधिभोग प्रमाण पत्र प्रस्तुत किया गया है, वह Part !T Block-i & Part Residency 8॥007 परियोजना से सम्बंधित है, जिसका onyx iT TOWER परियोजना से कोई सम्बंध नहीं है। शिकायतकर्तागण की परियोजना का मानचित्र विकास प्राधिकरण द्वारा स्वीकृत नहीं किया गया है। शिकायतकर्तागण द्वारा जनसूचना अधिकार अधिनियम के अधीन विकास प्राधिकरण से दिनांक 04.0920:9 को सूचना मांगी गयी थी, प्राप्त सूचना के अनुसार परियोजना का मानचित्र स्वीकृत नहीं हुआ है, क्योंकि विपक्षी ने विकास प्राधिकरण द्वारा लगायी गयी आपत्तियों का निराकरण नहीं किया है। आंशिक पूर्णता प्रमाण पत्र दिनांक 06.03.20i7 दोषपूर्ण व श्रमात्मक है। Mis Times Shopee Centre P.Ltd. द्वारा कोई बिल्डर बायर एग्रीमेंट निष्पादित नहीं किया गया है। आंशिक पूर्णता प्रमाण पत्र में परियोजना IMPERIA ॥20 OFFICE SUITES का उल्लेख नहीं किया गया है। इस आंशिक पूर्णता प्रमाण BE विनिर्दिष्ट रूप से Page 3 of ३4 E-Court
किसी परियोजना का नाम अंकित नहीं किया गया है। शिकायतकर्तागण से यूनिट्स के सम्बंध में एमओ.यू. मेसर्स इम्पीरिया स्ट्रक््चर लि. द्वारा किया गया है। मानचित्र स्वीकृति हेतु विकास प्राधिकरण को आवेदन M/s Times Shopee Centre P.Ltd. द्वारा आवेदन वर्ष 204 में दिया गया है। एम.ओ.यू में मेसर्स टाइम शापी सेन्टर प्रा.लि. का कोई उल्लेख नहीं है। IMPERIA H20 IT SPACE ONYX TOWER रेरा अधिनियम की धारा--3 के अधीन पंजीकरण योग्य है। विपक्षी आंशिक अधिभोग प्रमाण पत्र के आधार पर रेरा प्राधिकरण को भ्रमित करते हुए यह दावा प्रस्तुत कर रहा है कि परियोजना पंजीकरण योग्य नहीं है। विपक्षी ने आज तक परियोजना IMPERIA H20 IT SPACE ONYX TOWER का कोई भी पूर्णता / अधिभोग प्रमाण पत्र प्राप्त नहीं किया है। आंशिक ओसी M/s Times Shopee Centre P.Ltd. के पक्ष में जारी किया गया है। मेसर्स इम्पीरिया स्ट्रक््चर लि. व Mis Times Shopce Centre P.Ltd, दोनों भिन्न--भिन्न कम्पनी है, जिनका सी.आई.एन. नम्बर अलग-अलग 3 | अपने कथन के समर्थन में शिकायतकर्ता ने उपरोक्त शिकायत में मा. पीठ द्वारा पारित आदेश दिनांक 45.07.2022 की प्रति, विकास प्राधिकरण के पत्र दिनांकित 06.03.2047, 23.08.2044, 7.07.20i8, 04.08.2020, 07.09.2020, '4.05.2048, 07.08.2020, 27.07.20:8, जनसूचना अधिकार के अधीन प्राप्त सूचना दिनांकित 04.09.2049 दाखिल किया है। विपक्षी का पक्ष कथन / तर्क विपक्षी की ओर से लिखित कथन दिनांकित 04.04.2024, लिखित बहस दिनांकित 06.06.2024, जो पोर्टल पर दिनाक 30.07.2024 को अपलोड किया गया है, जो अत्यन्त धूमिल होने के कारण स्पष्ट रूप से पढ़ने योग्य नहीं है।
विपक्षी का कथन है कि परियोजना “इम्पीरिया एच.2ओ. आई.टी. स्पेस” है। M/s Times Shopee Centre P.Ltd. जिस भूमि पर परियोजना विकसित की जा रही है, उसका स्वामी है। विपक्षी केवल विकासकर्ता है। अधिभोग प्रमाण पत्र भूमि के स्वामी के पक्ष में जारी किया गया है। परियोजना में चरणबद्ध तरीके (phased manner) में विकास कार्य किया जा रहा है। रेरा अधिनियम की धारा-2 के स्पष्टीकरण के अनुसार चरणबद्ध तरीके (phased manner) से परियोजना विकसित एवं रेरा में पंजीकृत करायी जा सकती है। चरणबद्ध तरीके (phased manner) से निर्माण के कारण कुछ भवनों का निर्माण कार्य पूर्ण हो चुका है, जबकि कुछ भवनों का निर्माण कार्य लम्बित है। इसलिए विपक्षी ने अलग बिल्डिंग के लिए पूर्णता प्रमाण पत्र हेतु आवेदन प्रस्तुत किया है। विपक्षी के अनुसार रेरा अधिनियम की धारा--3(2)७) के प्राविधानों के अनुसार यदि अधिनियम & लागू होने से पूर्व पूर्णता प्रमाण पत्र प्राप्त a हो, तो ऐसी Page 4 0विव E-Court परियोजना का रेरा में पंजीयन कराया जाना आवश्यक नहीं है। परियोजना “इम्पीरिया एच.2ओ. आई.टी. स्पेस” का पूर्णता प्रमाण पत्र एवं अधिभोग प्रमाण पत्र दिनांक 06.03.2047 को जारी किया जा चुका है। विपक्षी के लिखित कथन के प्रस्तर--8 के अनुसार परियोजना “इम्पीरिया एच.2ओ. आई.टी. स्पेस” UMBRELLA PROJECTS IMPERIA ४20 के अंतर्गत आती है, जिसका पूर्णता प्रमाण पत्र अधिनियम के लागू होने के पहले ही जारी हो चुका है।
विपक्षी का यह भी कथन है कि रेरा प्राधिकरण की मा. पीठ द्वारा शिकायत संख्या ४८११44/03/724723/2024 सुखमल चन्द्र जैन बनाम इम्पीरिया स्ट्रक््चर प्रा. लि. एवं ॥४८२१44/04/88742/2022 पंकज कुमार बनाम इम्पीरिया स्ट्रक््चर प्रा.लि. के मामले में यह सम्प्रेक्षण किया जा चुका है कि परियोजना धारा-3 के अधीन पंजीकरण योग्य नहीं है। शिकायतकर्तागण ने केवल एम.ओ.यू. दाखिल किया है, भुगतान से सम्बंधित कोई रसीद दाखिल नहीं किया है। अपने तर्क के समर्थन में विपक्षी की ओर से मा. सर्वोच्च न्यायालय के निर्णय मेसर्स न्यूटेक प्रमोटर एण्ड डेवलपर्स लि. बनाम उ.प्र. राज्य सिविल अपील संख्या 6745-6749 / 2024 एवं मा. पंजाब एवं हरियाणा हाईकोर्ट के निर्णय इक्सपीरियन डेवलपर्स wife, बनाम स्टेट आफ हरियाणा cwe/7852/2022 का आश्रय लिया गया है। विधिक स्थिति सर्वप्रथम इस सम्बंध में विधिक स्थिति का veers करना समीचीन होगा। रेरा अधिनियम की धारा--3 में रियल see प्रोजेक्ट के पंजीकरण के सम्बंध 4 प्राविधान किया गया है। धारा-3 के प्राविधानों के अनुसार ऐसी परियोजना जो अधिनियम लागू होने की तिथि पर चल रही (Ongoing) परियोजना की श्रेणी में आती थी। वह परियोजना रेरा में पंजीकृत / पंजीकरण योग्य है। wy अधिनियम की aee3) के प्राविधानों के अनुसार योजना क्षेत्र के अंतर्गत कोई भी प्रमोटर किसी भी भवन, अपार्टमेंट या भूखण्ड को किसी भी प्रकार से विज्ञापित, विपणित, बुक, विकय अथवा विकय के लिए करार नहीं करेगा। धारा-3(3) के प्राविधान निम्नवत है:- Section 3-Prior registration of real estate project with Real Estate Regulatory Authority.
(2) No promoter shall advertise, market, book, sell or offer for sale, or invite persons to purchase in any manner any plot, apartment or building, as the case may be, in any real estate project or part of it, in any planning area, without = rgal estate Page 5 of 4 E-Court project with the Real Estate Regulatory Authority established under this Act: Provided that projects that are ongoing on the date of commencement of this Act and for which the completion certificate has not been issued, the promoter shall make an application to the Authority for registration of the said project within a period of three months from the date of commencement of this Act. रेरा अधिनियम की धारा--3(4) के प्रथम UGH के अवलोकन से यह प्रतीत होता है कि ऐसी परियोजनाएं जो अधिनियम लागू होने की तिथि पर चल रही (Ongoing) परियोजना की श्रेणी में आती थी और जिनका पूर्णता प्रमाण-पत्र जारी नहीं हुआ था, उन परियोजनाओं का रेरा में पंजीकरण कराया जाना अनिवार्य था। अधिनियम के प्रारम्भ होने की तिथि 04.05.2046 है अर्थात जिस परियोजना का पूर्णता प्रमाण पत्र दिनांक oros20i6 से पूर्व जारी हो चुका था। उस परियोजना को चल रही (Ongoing) परियोजना नहीं माना जाएगा और उसका पंजीकरण अनिवार्य नहीं होगा।
मा. उ.प्र. रेश अपीलीय अधिकरण ने sige अग्रवाल बनाम मेसर्स उप्पल चढ्ढा हाईटेक डेवलपर्स प्रालि. अपील संख्या 575,/2024 निर्णीत दिनांक 37.05.2023 के मामले में निर्णय के प्रस्तर-7.26 में यह अवधारित किया है कि यदि परियोजना का पूर्णता/अधिभोग प्रमाण पत्र अधिनियम के प्रभावी होने की तिथि अर्थात 0.05.206 को जारी नहीं हुआ था तो परियोजना चल रही (Ongoing) परियोजना मानी जाएगी और उसका रेरा में पंजीकरण कराया जाना अनिवार्य होगा। इस निर्णय में मा. अपीलीय अधिकरण ने अर्बन प्लानिंग एण्ड डेवलपमेंट एक्ट 4973 उ.प्र. अपार्टमेंट (प्रमोशन आफ कस्ट्रसन, ओनरशिप एण्ड मेंटीनेंस) एक्ट, 200, रेरा एक्ट एवं Geu, 2046 के प्राविधानों पर सम्यक विचार करने के उपरांत अपार्टमेंट एक्ट, 2040 की धारा--4(5) के स्पष्टीकरण पर विचार करने के उपरांत यह अवधारित किया है कि “पूर्णता” का aura सम्पूर्ण निर्माण अथवा एक स्वतंत्र ब्लाक के निर्माण से है। परियोजना के एक ब्लाक के निर्माण का पूर्णता प्रमाण पत्र प्राप्त करना केवल कब्जा प्रदान करने के उद्देश्य से होता है। एक ब्लाक का पूर्णता / अधिभोग प्रमाण पत्र जारी होने के बावजूद जब तक परियोजना का सम्पूर्ण निर्माण / विकास कार्य पूर्ण नहीं हो जाता, तब तक परियोजना चल रही (Ongoing) परियोजना हीं मानी जाएगी। चल रही (Ongoing) परियोजना को रेरा अधिनियम, 2046 के अंतर्गत परिभाषित नहीं किया गया है। रेरा नियमावली, 2046 के नियम- -2()(h) में चल रही (ONGOING) परियोजना को परिभाषित करते हुए यह प्राविधानित किया गया है कि किन परियोजनाओं का रेरा में पंजीकरण आवश्यक है और किन परियोजनाओं का रेरा में पंजीकरण आवश्यक नहीं है। रेरा नियमावली, 2046 के नियम -2(3)|9) निम्नवत हैः-- a a Page 6 034 E-Court
(h) "ongoing project" means a project where development is going on and for which completion certificate has not been issued but excludes such projects which fulfill any of the following criteria on the date of notification of these rules: (i) where services have been handed over to the Local Authority for maintenance. (ii) where common areas and facilities have been handed over to the Association for the Residents’ Welfare Association for maintenance. (iii) where all development work have been completed and sale/lease deeds of sixty percent of the apartment/houses/plots have been executed. (iv) where all development works have been completed and application has been filed with the competent authority for issue of completion certificate.
रेरा नियमावली, 20i6 के नियम--4(2) के प्राविधानों के अनुसार नियमावली राजपत्र में प्रकाशन की तिथि से प्रभावी होगी। नियमावली का प्रकाशन राजपत्र में NOTIFICATION NO. 438/ViI!-3-26-65 VIVIDH-6, DATED- 27-0-2046, PUBLISHED IN U.P. GAZETTE, EXTRA PART-4, SECTON (ka), DATED- 27-0-206 को किया गया। इस प्रकार wi नियमावली, 20i6 & प्रभावी होने की तिथि 27.40.206 है। रेरा नियमावली, 20i6 के नियम -2()/) के प्राविधानों के अनुसार नियमावली के अधिसूचित होने की तिथि 27.4020I6 को जिस परियोजना का पूर्णता प्रमाण पत्र जारी नहीं हुआ था वह परियोजना चल रही (Ongoing) परियोजना की श्रेणी में आएगी और उसका रेरा में पंजीकरण कराया जाना अनिवार्य होगा। नियम--2(3)(0)0),(/,(॥) & (४) में 04 मापदण्ड बताये गये हैं। इन चारों मापदण्डों में से किसी भी मापदण्ड को पूरा करने वाली परियोजना, पूर्णता प्रमाण पत्र जारी न होने के बावजूद चल रही (Ongoing) परियोजना की श्रेणी से बाहर मानी जाएगी और ऐसी परियोजना का रेरा में पंजीकरण कराया जाना अनिवार्य नहीं होगा। रेरा अधिनियम की धारा-3 के प्राविधानों का प्रमोटर द्वारा उल्लंघन किए जाने पर arse में शास्ति एवं दण्ड का प्राविधान किया गया है। यदि प्रमोटर द्वारा परियोजना ar a में पंजीकरण नहीं कराया जाता तो उस पर शास्ति, जो परियोजना के लागत का io प्रतिशत हो सकती है, अधिरोपित किए जाने का प्राविधान है। यदि प्रमोटर द्वारा अधिरोपित शास्ति जमा नहीं की जाती तो प्रमोटर का दाण्डिक अभियोजन कर 03 वर्ष के कारावास तक दण्ड का प्राविधान है। धारा-59 के प्राविधान निम्नवत है:- Section 59- Punishment for non registration under section 3. (2) If any promoter contravenes the provisions of section 3, he shall be liable to a penalty which may extend up to ten per cent. of the estimated cost of the real estate project as determined by the Authority.
(2) If any promoter does not comply with the orders, decisions or directions issued under sub-section (3) or continues to violate the provisions of section 3, he shall be punishable ८222 prisonment for a Page 7 ०विव E-Court term which may extend up to three years or with fine which may extend up to a further ten per cent. of the estimated cost of the real estate project, or with both. निष्कर्ष उभयपक्षों के अभिकथनों, प्रस्तुत किए गए साक्ष्य एवं मौखिक बहस में प्रस्तुत तर्कों के आधार पर निम्नलिखित अवधार्य बिन्दु उत्पन्न होता हैः-- 4. क्या परियोजना रेरा में पंजीकृत,/ पंजीकरण योग्य है? अवधार्य बिन्दु--4 शिकायतकर्तागण का कथन है कि विपक्षी ने परियोजना का रेरा में पंजीकरण नहीं कराया है। बिना पंजीकरण कराये परियोजना में युनिटे कय--विकय की जा रहीं हैं। निर्धारित समय में कब्जा नहीं दिया जा रहा है। विकय अनुबंध की शर्तों का उल्लंघन किया जा रहा है। विपक्षी द्वारा tar अधिनियम की धारा-3 के प्राविधानों का उल्लंघन किया गया है। अतः उसके विरूद्ध विधिक कार्यवाही की जाये। विपक्षी का कथन है कि उसकी परियोजना का रेरा में पंजीकरण कराया जाना अनिवार्य नहीं है। अधिनियम लागू होने की तिथि पर विपक्षी की परियोजना चल रही (Ongoing) परियोजना की श्रेणी में नहीं आती थी। क्योंकि अधिनियम लागू होने से पूर्व ही दिनांक 06.03.2047 को विकास प्राधिकरण द्वारा परियोजना का अधिभोग प्रमाण पत्र जारी किया जा चुका था। अब इस तथ्य का परीक्षण करना है कि कया विपक्षी की परियोजना धार 3(2)(b) सपठित fra—2(4)(h) रेरा नियमावली के अधीन रेरा में पंजीकरण से मुक्त है।
विपक्षी की ओर से पंजीकरण से छूट का मुख्य आधार यह बताया गया है कि परियोजना का अधिभोगपूर्णता प्रमाण पत्र दिनोक 06.03.207 को जारी किया जा चुका था। इस अधिभोग,/पूर्णता प्रमाण पत्र के आधार पर मा. प्राधिकरण की पीठ द्वारा शिकायत संख्या ॥३(४44/03/724723/2024 सुखमल चन्द्र जैन बनाम इम्पीरिया RR प्रा.लि. एवं NCRI44/02/8872/2022 पंकज कुगार बनाम इम्पीरिया er wife. के मामले में यह माना जा चुका है कि परियोजना धारा--3 के अपवाद के अधीन आती है क्योंकि प्रमोटर द्वारा अधिभोग / पूर्णता प्रमाण पत्र प्राप्त किया जा चुका था। विपक्षी के उपरोक्त तर्क का खण्डन करने हेतु शिकायतकर्तागण की ओर से कहा गया कि उपरोक्त शिकायतों में मा. पीठ द्वारा ऐसा कोई मत व्यक्त नहीं किया गया है कि परियोजना रेरा में पंजीकरण योग्य नहीं है। इसके विपरीत शिकायत संख्या ८४44/09/6469/2020 अभियांक सिन्हा बनाम इस्पीरिया स्ट्रक््चर लि. में मा. पीठ-4, एन.सी.आर. द्वारा अपने आदेश दिनांक १5.07.2022 में परियोजना को पंजीकरण योग्य पाते हुए विपक्षी को आदेशित किया था कि विपक्षी 03 माह के अन्दर परियोजना का रेरा में पंजीकरण कराये, इसके बावजूद पंजीकरण नहीं कराया गया है। उभयपक्षों के तर्क के आधार पर अभिलेख के अवलोकन से प्रकट होता है कि विपक्षी ने अपने लिखित कथन में उल्लिखित निर्णयों की प्रति "he | Page 8 of 4 E-Court शिकायतकर्ता ने अपने कथन के समर्थन में उल्लिखित शिकायत में पारित निर्णय की प्रति दाखिल की गयी है।
विपक्षी द्वारा उद्धृत दोनों निर्णयों को रेरा पोर्टल पर अवलोकन से प्रकट होता है कि सुखमल चन्द्र जैन की उपरोक्त शिकायत के मामले में मा. पीठ द्वारा ऐसा कुछ भी अपवधारित नहीं किया गया है कि परियोजना रेरा में पंजीकरण योग्य नहीं है। मा. पीठ ने अपने निर्णय दिनांक 27.04.2022 में मात्र मेसर्स We प्रमोटर एण्ड डेवलपर्स प्रा.लि. के मामले में मा. सर्वोच्च न्यायालय द्वारा पारित निर्णय के प्रस्तर-54 को उद्धृत किया है। विपक्षी ने मा. पीठ के आदेश का भ्रमित अर्थ निकालते हुए अपने लिखित कथन के प्रस्तर-40 में मेसर्स wee प्रमोटर एण्ड डेवलपर्स प्रा.लि. के मामले में मा. सर्वोच्च न्यायालय द्वारा पारित निर्णय के प्रस्तर-54 को मा. पीठ का अवधारण मानते हुए अभिकथित किया है। लिखित कथन के प्रस्तर-40 में विपक्षी ने यह उल्लेख किया है कि मा. पीठ ने अवधारित किया है कि परियोजना पंजीकरण योग्य नहीं है। तो इस सम्बंध में उल्लेखनीय है कि यह मा. पीठ का कोई मत नहीं है बल्कि मा. सर्वोच्च न्यायालय द्वारा पारित निर्णय के प्रस्तर-54 का उद्धरण मात्र है।
जहाँ तक दूसरे निर्णय ॥८४१44/04/88742/2022 पंकज कुमार बनाम इम्पीरिया rr प्रालि. का सम्बंध है तो पोर्टल पर उपलब्ध इस शिकायत में पारित निर्णय एवं आदेश दिनांक 02.::.2022 को अवलोकन से प्रकट होता है कि मा. पीठ ने अपने आदेश में ऐसा कोई मत व्यक्त नहीं किया है कि परियोजना रेरा में पंजीकरण योग्य नहीं है। मा. पीठ ने शिकायत को ABEYANCE में रखते हुए 03 माह के अन्दर परियोजना के पंजीकरण के सम्बंध में जांच एवं कार्यवाही किए जाने का आदेश पारित किया गया है a पीठ ने सचिव रेरा को यह सुनिश्चित करने हेतु निर्देशित किया गया है कि परियोजना रेरा में पंजीकरण योग्य है अथवा नहीं? इस प्रकार विपक्षी द्वारा अपने तर्क के समर्थन में जिन शिकायतों में पारित आदेशों का उल्लेख किया गया है, उन दोनों ही शिकायतों में मा. पीठ द्वारा ऐसा कोई आदेश पारित नहीं किया गया है कि परियोजना रेरा में पंजीकरण योग्य नहीं है। इस प्रकार विपक्षी ने अपने तर्क के समर्थन में जिन 02 शिकायतों का उल्लेख किया है, उन शिकायतों में पारित आदेश से विपक्षी के तर्क का किसी भी प्रकार से समर्थन नहीं होता। इसके विपरीत शिकायतकर्तागण ने अपने तर्क के समर्थन में शिकायत संख्या NCRI44/09/669/2020 अभियांक सिन्हा बनाम इम्पीरिया स्ट्रक््चर लि. में मा. de, एन.सी.आर. द्वारा पारित आदेश दिनांक 45.07.2022 का आश्रय लिया है।
मा. We, एन.सी.आर. द्वारा पारित उपरोक्त आदेश दिनांक 45.07.2022 के अवलोकन से परिलक्षित होता है कि मा. पीठ ने 03 माह के अन्दर परियोजना का रेरा में पंजीकरण कराने हेतु विपक्षी को आदेशित किया गया। साथ-ही--साथ रेरा में पंजीकरण न कराये जाने के लिए विपक्षी के विरूद्ध विधिक कार्यवाही करने हेतु सचिव रेरा को निर्देशित भी किया गया। मा. पीठ के आदेश दिनांक 45.07.2022 के प्रवर्तनशील भाग के बिन्दु संख्या 2. 3 व 4 का उल्लेख किया A= >सभीचीन होगा। बिन्दु 2, 3 व 4 निम्नवत Page 9 एणावि4 E-Court “2. विपक्षी को आदेशित किया जाता है कि प्रश्नगत परियोजना का आगामी 3 माह के अंतर्गत अपनी परियोजना को er में पंजीकृत कराना सुनिश्चित करें। 3... सचिव, रेरा, विपक्षी द्वारा परियोजना को रेरा में पंजीकृत न किए जाने हेतु ka अधिनियम के अनुसार विधिसंम्यक कार्यवाही करें। 4. इस आदेश की एक प्रति सचिव, रेरा को अग्रतर कार्यवाही हेतु प्रेषित की जाये।” इस प्रकार मा. पीठ क॑ आदेश से स्पष्ट है कि मा. पीठ ने परियोजना के पंजीकरण योग्यता पर अपना विधिक मश्तिष्क प्रयोग करने के उपरांत परियोजना को रेरा में पंजीकरण योग्य पाया है। विपक्षी को 3 माह के अन्दर परियोजना को रेरा में पंजीकरण कराये जाने का आदेश भी दिया गया है। परियोजना का रेरा में पंजीकरण न कराये जाने के कारण विपक्षी के विरूद्ध विधिक कार्यवाही करने हेतु सचिव रेरा को निर्देशित भी किया गया है। मा. पीठ के उपरोक्त आदेश के बावजूद विपक्षी ने परियोजना का आज तक रेरा में पंजीकरण नहीं कराया है।
विपक्षी का कथन है कि उसकी पश्योजना का पूर्णता प्रमाण पत्र /अधिभोग प्रमाण पत्र दिनांक 06.03.2077 को जारी किया जा चुका है। इस कारण परियोजना रेश में पंजीकरण योग्य नहीं है। इस सम्बंध में विपक्षी की ओर से लिखित कथन के प्रस्तर--6 में रेरा अधिनियम की धारा-3(2)/) के प्राविधानों पर विशेष बल दिया गया है। धारा-3(2)(0) के प्राविधानों के अवलोकन से प्रकट होता है कि जिन परियोजनाओं का पूर्णता प्रमाण पत्र अधिनियम के प्रारम्भ की तिथि से पूर्व प्राप्त हो चुका था, उन परियोजनाओं का रेरा में पंजीकरण कराया जाना अनिवार्य नहीं होगा | घारा--3(3) के प्रथम परन्तुक के प्राविधानों के अनुसार अधिनियम के प्रारम्भ होने की तिथि पर जिस परियोजना का पूर्णता प्रमाण पत्र जारी नहीं हुआ था, वह परियोजना चल रही (ONGOING) परियोजना मानी जाएगी, जिसका 63 माह के अन्दर रेरा में पंजीकरण कराया जाना अनिवार्य होगा। धारा-३(2)) व धारा-3(3) के प्रथम परन्तुक दोनों ही प्राविधानों में चल रही (ONGOING) परियोजना /रेरा में पंजीकरण योग्य परियोजना के निर्धारण तथा पूर्णता प्रमाण पत्र जारी होने के लिए सारवान तिथि अधिनियम के प्रारम्भ होने की तिथि अर्थात्त दिनांक 04.05.2046 दी गयी है। मा. उ.प्र. WT अपीलीय अधिकरण ने भी अंशुल अग्रवाल बनाम मेसर्स उप्पल चढ्ढा हाईटेक डेवलपर्स प्रा.लि. अपील संख्या 575,/2024 निर्णीत दिनांक 37.05.2023 के मामले में निर्णय के प्रस्तर -7.26 में यह अवधारित किया है कि यदि परियोजना का पूर्णता /अधिमोग प्रमाण पत्र अधिनियम के प्रभावी होने की तिथि अर्थात 04.05.206 को जारी नहीं हुआ था तो परियोजना चल रही (Ongoing) परियोजना मानी जाएगी और उसका रेरा में पंजीकरण कराया ‘Ele 222 होगा। Page १0 ठविव शक E-Court
विपक्षी के उपरोक्त तर्क के आधार पर अभिलेख के अवलोकन से परिलक्षित होता है कि विपक्षी की ओर से कोई पूर्णता प्रमाण पत्र प्रस्तुत नहीं किया गया है। विपक्षी की ओर से जो प्रमाण पत्र प्रस्तुत किया गया है वह अधिभोग प्रमाण पत्र है। यह अधिभोग प्रमाण पत्र भी आंशिक है जो कि पूरे ब्लाक का न होकर, पार्ट आई. टी. wisi व पार्ट रेजीडेंसी ब्लाक-4 के सम्बंध में जारी किया गया है। इसका अभिप्राय यह है कि परियोजना में कई ब्लाक है। es में जो निर्माण कार्य किया गया है और जिसका आंशिक अधिभोग प्रमाण पत्र जारी किया गया है। आंशिक अधिभोग प्रमाण पत्र आई.टी. ब्लाक-4 व रेजीडेंसी ब्लाक-॥ के एक अंश का है अर्थात आई.टी. ब्लाक--4 व रेजीडेंसी ब्लाक-4 के दूसरे अंश का निर्माण कार्य पूरा नहीं है। यदि एक परियोजना में 4 ब्लाक है और उसमें से एक ब्लाक के एक अंश का अधिभोग प्रमाण पत्र प्राप्त कर लिया जाता है तो भी मात्र एक ब्लाक के आंशिक अधिभोग प्रमाण पत्र के आधार पर परियोजना का शेष निर्माण कार्य पूर्ण नहीं माना जाएगा। जब तक चारों ब्लाक का निर्माण कार्य पूर्ण नहीं हो जाता और उसका पूर्णता प्रमाण पत्र/अधिभोग प्रमाण पत्र जारी नहीं हो जाता, तब तक परियोजना धारा-3 के अधीन चल रही (Ongoing) परियोजना मानी जाएगी और उसका रेरा में पंजीकरण कराया जाना अनिवार्य होगा।
यदि तर्क के लिए यह मान भी लिया जाये कि दिनांक 06.03.2047 को सम्पूर्ण परियोजना का पूर्णता प्रमाण पत्र,/अधिभोग प्रमाण पत्र प्राप्त कर लिया गया है, तब भी परियोजना धारा-3 के अधीन चल रही (Ongoing) परियोजना ही मानी जाएगी, क्योंकि अधिनियम के प्रारम्भ होने की तिथि 0.05.20:6 है अर्थात आंशिक अधिभोग प्रमाण पत्र अधिनियम के प्रारम्भ होने की तिथि के बाद का होगा। इसलिए इस आंशिक अधिभोग प्रमाण पत्र के आधार पर विपक्षी की परियोजना को चल रही (Ongoing) परियोजना की श्रेणी से बाहर नहीं माना जा सकता। विपक्षी की परियोजना अधिनियम के प्रारम्भ होने की तिथि 02.05.20:6 को चल रही (Ongoing) परियोजना मानी जाएगी और इसका रेरा में पंजीकरण कराया जाना अनिवार्य होगा। इसीलिए मा. पीठ ने भी अपने उपरोक्त आदेश दिनांक 5.07.2022 में परियोजना को पंजीकृत कराने हेतु विपक्षी को निर्देशित किया गया है। अन्यथा भी इस आंशिक अधिभोग प्रमाण पत्र दिनांकित 06.03.2047 के अवलोकन से परिलक्षित होता है कि यह आंशिक अधिभोग प्रमाण पत्र Mis Times Shopee Centre P.Ltd. ® पक्ष में निर्गत किया गया है। विपक्षी इम्पीरिया war लि. के पक्ष में कोई आंशिक अधिभोग प्रमाण पत्र जारी नहीं किया गया है।
विपक्षी का कथन है कि Mis Times Shopee Centre P.Ltd. परियोजना से सम्बंधित भूमि के स्वामी है और विपक्षी विकासकर्ता है। जब परियोजना से सम्बंधित भूमि का स्वामी कोई अन्य व्यक्ति होता है और परियोजना का विकास किसी अन्य व्यक्ति द्वारा किया जाता है तो ऐसे मामले में दोनों पक्षों के मध्य wage dae एग्रीमेंट या कोई अन्य अनुबंध अथवा कोई एम.ओ.यू. निष्पादित किया जाता है। विपक्षी से जब सुनवाई के दौरान इस सम्बंध में पूछा गया तो उसके द्वारा स्वीकार किया गया कि उसने ऐसा कोई प्रपत्र दाखिल नहीं किया है। जबकि विपक्षी को अपना पक्ष प्रस्तुत करने तथा प्रपत्र प्रस्तुत BA ने. का पर्याप्त एवं युक्तियुक्त अवसर दिया गया। 77 Page ॥4 एव E-Court
इस बिन्दु पर मा. उ.प्र. रेश अपीलीय अधिकरण द्वारा अंशुल अग्रवाल बनाम मेसर्स उप्पल deer हाईटेक डेवलपर्स प्रालि. अपील संख्या 575 ,/ 2024 निर्णीत दिनांक 37.05.2023 & मामले में निर्णय के प्रस्तर- 7.49 का उल्लेख किया जाना समीचीन होगा। मा. उ.प्र. रेश अपीलीय अधिकरण ने निर्णय के प्रस्तर-7.49 में अर्बन प्लानिंग एण्ड डेवलपमेंट एक्ट i973 उप्र. अपार्टमेंट (प्रमोशन आफ कस्ट्रसन, ओनरशिप एण्ड मेंटीनेंस) एक्ट, 2040, रेरा एक्ट एवं Bea, 2046 के प्राविधानों पर सम्यक विचार करने के उपरांत अपार्टमेंट एक्ट, 2040 की धारा-4(5) के स्पष्टीकरण पर विचार करने के उपरांत यह अवधारित किया है कि “पूर्णता” का अभिप्राय सम्पूर्ण निर्माण अथवा एक स्वतंत्र ब्लाक के निर्माण से है। परियोजना के एक ब्लाक के निर्माण का पूर्णता प्रमाण पत्र प्राप्त करना केवल कब्जा प्रदान करने के उद्देश्य से होता है। एक ब्लाक का पूर्णता/अधिभोग प्रमाण पत्र जारी होने के बावजूद जब तक परियोजना का सम्पूर्ण निर्माण/विकास कार्य पूर्ण नहीं हो जाता, तब तक परियोजना चल रही (Ongoing) परियोजना ही मानी जाएगी | विपक्षी की ओर से अपने लिखित कथन के प्रस्तर- -4, 5 एवं 6 में कथन किया गया है कि उसके द्वारा परियोजना का फेज वाइज विकास किया जा रहा है। विपक्षी के अनुसार रेरा अधिनियम की धारा--2 के स्पष्टीकरण के अनुसार प्रत्येक फेज का पृथक पंजीकरण कराया जा सकता है।
विपक्षी के इस तर्क के आधार पर विधिक स्थिति पर विचार किया गया। धारा--2 के अधीन विभिन्न परिभाषाएं दी गयी है। इस धारा में कोई स्पष्टीकरण नहीं है। अधिनियम की धारा--3 के स्पष्टीकरण में परियोजना के फेज वाइज विकास के सम्बंध में स्थिति स्पष्ट की गयी है, जिसके अनुसार प्रत्येक फेज अकेले अपने आप में एक परियोजना होगी। विपक्षी का कथन है उसके द्वारा परियोजना का फेज वाइज विकास किया जा रहा है, परन्तु विपक्षी द्वारा ऐसा कोई अभिलेख प्रस्तुत नहीं किया गया है, जिससे यह प्रकट हो कि परियोजना का कितने फेजेज में विकास किया जा रहा है। किस फेज में क्या-क्या निर्माण किया जा रहा है। कितने फेज का निर्माण हो चुका है कितने फेज का निर्माण बाकी है। शिकायतकर्तागण को आवंटित यूनिट किस फेज के अंतर्गत आती है। यूनिट आवंटन के सम्बंध में पत्रावली पर उपलब्ध अग्रणी शिकायत कमांक--4 के एम.ओ.यू. के अवलोकन से परिलक्षित होता है कि TAA के पेज--2 पर परियोजना का नाम PROJECT OF ॥/5 OFFICE SPACE CALLED ‘ONYX’ अंकित है। विपक्षी द्वारा शिकायतकर्ता के पक्ष में जारी अदेयता प्रमाण पत्र दिनांकित 2644. 20i8 में परियोजना का नाम “won उल्लिखित है। पत्रावली पर एक त्रिपक्षीय सब--लीज--डीड है जो ग्रेटर नोएडा औद्योगिक विकास प्राधिकरण, टाइम शापी सेन्टर wife. एवं आवंटी / शिकायतकर्ता के मध्य निष्पादित किया जाना तात्पर्यित है, जिसमें परियोजना का नाम tz0 rr park” उल्लिखित है। इसी प्रकार अन्य शिकायतों मे भी afer अभिलेखों में परियोजना का ff नाम दिया गया है| विपक्षी की ओर से अपने लिखित कथन में यह भी अभिकथन किया गया है कि शिकायतकर्तागण ने अपने पक्ष में रजिस्ट्री कराकर कब्जा भी Ge fear है इसके Page 42 ०तविव E-Court
बावजूद शिकायत प्रस्तुत की गयी है। इसलिए शिकायतकर्तागण की शिकायत पश्चातवर्ती विचार (afterthought) का परिणाम है, जिसमें कोई सार नहीं है। विपक्षी की ओर से परियोजना का अधिभोग प्रमाण पत्र जारी होने के आधार पर रेरा में पंजीकरण से छूट का दावा किया जा रहा है। विपक्षी के अनुसार परियोजना पूर्ण हो चुकी है, जिसका अधिभोग प्रमाण पत्र दिनांक 06.03.2047 को जारी हो चुका है इसलिए रेरा में पंजीकरण की आवश्यकता नहीं है और इसीलिए रेरा में पंजीकरण नहीं कराया गया है। शिकायतकर्ता की ओर से ग्रेटर नोएडा औद्योगिक विकास प्राधिकरण द्वारा जारी पत्र दिनांक 23.03.2044, 44.07.2048, 27.07.208, 07.08.2020, 07.09.2020, 04.08.2020 एवं 74.05.20i8 Beda far है, जिसके अवलोकन से प्रकट होता है कि विकास प्राधिकरण द्वारा दिनांक 23.03.204 को प्लाट--44--45, SECTOR- KNOWLEDGE PARK-V, GREATER NOIDA पर परियोजना का मानचित्र स्वीकृत किया गया। अन्य विभिन्न पत्रों के अवलोकन से प्रकट होता है कि विपक्षी द्वारा प्राधिकरण के समक्ष पुनरीक्षित मानचित्र स्वीकृत कराये जाने हेतु आवेदन प्रस्तुत किए गए हैं जो प्राधिकरण के समक्ष विचारार्थ लम्बित है। पत्र दिनांकित 4.05.20i8 के अवलोकन से प्रकट होता है कि मानचित्र परिवर्तन हेतु प्रस्तुत किए गए आवेदन पर विचार करने के उपरांत विकास प्राधिकरण ने अपने पत्र दिनांक 44.05.208 में कुल 45 आपत्तियां अंकित करते हुए विपक्षी से आपत्तियों को दूर करने की अपेक्षा की गयी है।
शिकायतकर्तागण द्वारा जनसूचना अधिकार के अधीन नियोजन अनुभाग के सहायक जनसूचना अधिकारी के vais: नियो०,/आ र०0टी0आई0 / 2049 / 5829 दिनांक 04.09.2049 के माध्यम से प्राप्त जनसूचना के अनुसार भूखण्ड संख्या 44-45, SECTOR- KNOWLEDGE PARK-V, GREATER NOIDA पर टाइम शापी सेन्टर प्रा. लि. द्वारा पुनरीक्षित मानचित्र स्वीकृति हेतु आवेदन किया गया है, जो वर्तमान तक मानचित्र स्वीकृत नहीं हुए हैं। उपरोक्त विवेचना एवं विश्लेषण से स्पष्ट है कि विपक्षी की परियोजना अधिनियम लागू होने की तिथि पर चल रही (Ongoing) परियोजना थी। आज भी परियोजना पूर्ण नहीं हुई है। पुनरीक्षित मानचित्र स्वीकृति हेतु विकास प्राधिकरण के समक्ष विचाराधीन है। मा. पीठ ने अपने आदेश दिनांक 45.07.2022 में पहले भी विपक्षी को 03 माह के अन्दर रेरा में परियोजना पंजीकरण कराने हेतु निर्देशित किया जा चुका है, इसके बावजूद विपक्षी द्वारा अभी तक परियोजना का पंजीकरण नहीं कराया गया है। अतः घर खरीददारों /आवंटीगण के हितों की संरक्षा के लिए परियोजना का रेरा में पंजीकरण कराया जाना आवश्यक BE. Page 43 of ॥4 E-Court आदेश शिकायतकर्तागण की शिकायतें स्वीकार की जाती हैं। परियोजना एक चल रही (Ongoing) परियोजना है। अतः परियोजना का रेरा में पंजीकरण होना आवश्यक है। पत्रावली पंजीकरण के सम्बंध में अग्रिम कार्यवाही हेतु सचिव, उ.प्र. रेरा को प्रेषित की जाये। DA दिनांक: 24.08.2024 (हरीश त्रिपाठी) न्यायनिर्णायक अधिकारी Page 34 ०4