gives to the applicant being a licensee an undertaking that it is competent to, and will, within twenty-four months from the said date, afford to him a supply of electricity sufficient for his requirements pursuant to his application; or
shows to the applicant that the electricity required by him pursuant to his application could be more economically obtained within a reasonable time from another appropriate source;
gives to the applicant being a licensee an undertaking that within twenty-four months from the said date either the station to which the application pertains will become a controlled station in terms of section 34, or the Board will make a declaration to the applicant in terms of section 35 offering him a supply of electricity sufficient for his requirements pursuant to his application, or the Board will make a declaration to him in terms of section 36; or
shows to the applicant that the electricity required by him pursuant to his application could be more economically obtained within a reasonable time from another appropriate source or by other appropriate means;
gives to the applicant being a licensee an undertaking that within eighteen months from the said date either the station to which the application pertains will become a controlled station in terms of section 34 or the Board will make a declaration to him in terms of section 36; or
shows to the applicant that the electricity required by him pursuant to his application could be more economically obtained within a reasonable time from another appropriate source or by other appropriate means.
(2)
There shall be stated in every application under this section such particulars as the Board may reasonably require of the station, plant or works, as the case may be, in respect of which it is made, and where consent is given thereto, in acting in pursuance of such consent, the applicant shall not, without the further consent of the Board, make any material variation in the particulars so stated.
[(2-A) The Board shall, before giving consent under sub-section (1), to the establishment or acquisition of a new generating station or to the extension or replacement of any major unit of plant or works, consult the Authority, in cases where the capacity of the new generating station or, as the case may be, the additional capacity proposed to be created by the extension or replacement exceeds twenty-five thousand kilowatts.] [ Inserted by Act 115 of 1976, Section 26 (w.r.e.f. 8.10.1976).]
(3)
Any difference or dispute arising out of the provisions of this section shall be referred to the arbitration of the Authority.